Enhancing Grid Resilience for Giga-Watt Scale Data Centers Using High Voltage Circuit Breaker Operated Braking Resistors
arXiv preprint (Black & Veatch / University of Central Missouri) · Soham Ghosh, Mohammad Ashraf Hossain Sadi
The work addresses the grid frequency and voltage rise that follows when hundreds of megawatts of voltage-sensitive IT load transfer to UPS during a transmission voltage dip, and proposes braking resistors switched by high-voltage circuit breakers at the data-centre transmission substation.
CC BY 4.0: share with attribution
On this page
Overview
As hyperscale and co-located data centres scale, the grid sees large, voltage-sensitive IT loads with plant sizes ranging from 500 MW to 2 GW. A sudden loss of these loads as they switch to on-site UPS during a grid voltage excursion causes a grid frequency rise from generation and load imbalance, and a voltage rise because less power is flowing through the network. In the July 2024 incident about 1,500 MW of voltage-sensitive demand disconnected after six voltage depressions from automatic reclosing on a 230 kV line; frequency peaked at 60.047 Hz and voltage reached 1.07 pu before shunt capacitors were withdrawn.
The proposed remedy is braking resistors switched by high-voltage circuit breakers at the data-centre transmission substation, temporarily absorbing the lost load so that the imbalance is staggered in time. Simulations on a test bed with a gigawatt-scale data-centre cluster on a 345 kV network, for different synchronous/inverter-based generation mixes, show that brief resistor insertion limits the rate of change of frequency while governor response and capacitor switching act. Resistor insertion for 0.25-0.85 seconds sufficiently reduced rate of change of frequency and gave time for primary governor response and capacitor switching.
Illustrative scenario: five 200 MW data centres with a 1:1 IT to non-IT split give a maximum load drop of 500 MW at the substation when ANSI 27/59 relays transfer IT loads to UPS. For a 500 MW IT-load loss the largest single-stage braking resistor tested was 250 MW (half the IT load); in the IBR-rich case a 370 MW multi-stage bank (130, 130 and 110 MW) reduced the maximum step change from 250 MW to 130 MW. A precedent cited is the Bonneville Power Administration 1400 MW braking resistor at Chief Joseph substation.
The finding is that multi-stage braking resistors are more effective than a single stage in inverter-rich systems. Limits: it is a conceptual application; the authors list thermal adequacy, cycling, stress testing in regions where IBRs operate in grid-following mode and other items as future work. It is a preprint.
Key points
- Data-centre plant sizes are cited as ranging between 500 MW and 2 GW.
- Resistor insertion for 0.25-0.85 seconds sufficiently reduced rate of change of frequency and gave time for primary governor response and capacitor switching.
- In the July 2024 incident about 1,500 MW of voltage-sensitive demand disconnected after six voltage depressions from automatic reclosing on a 230 kV line; frequency peaked at 60.047 Hz and voltage reached 1.07 pu.
- Illustrative scenario: five 200 MW data centres with a 1:1 IT to non-IT split give a maximum load drop of 500 MW at the substation when ANSI 27/59 relays transfer IT loads to UPS.
- For a 500 MW IT-load loss the largest single-stage braking resistor tested was 250 MW; in the IBR-rich case a 370 MW multi-stage bank (130, 130 and 110 MW) reduced the maximum step change from 250 MW to 130 MW.
- Precedent cited: the Bonneville Power Administration 1400 MW braking resistor at Chief Joseph substation.
Using it in design
- In gigawatt-scale data-centre interconnection studies, add the load-loss scenario from IT load transferring to UPS in a voltage dip (for example 5 × 200 MW with a 1:1 split giving 500 MW) to the grid frequency and voltage analysis.
- In inverter-rich grids evaluate multi-stage braking resistor banks (such as 130/130/110 MW) against a single stage; insertion time was in the 0.25-0.85 s range.
- Coordinate ANSI 27/59 relay settings and UPS transfer thresholds with grid resilience at the point of connection.
Who should read it
Grid engineers and data-centre designers planning gigawatt-scale data-centre interconnection and grid resilience.
Document contents
- I. Introduction (A. Research motivation, B. Manuscript contribution)
- II. Non-Voltage Sensitive Load Ride Through
- III. Test Bed System Description
- IV. Simulation Results and Discussion (A. Single machine system with single-stage resistive braking, B. Multi-machine system with single-stage resistive braking, C. IBR rich system with multi-stage resistive braking, D. System stability evaluation through eigenvalue trajectories, E. Investigating risk of motor stalling due to grid induced events)
- V. Conclusion and Future Work
Read the document
gw-dc-hv-breaker-braking-2025.pdf
CC BY 4.0: share with attribution
The document is provided unaltered because its licence permits redistribution.
Publication details
- Authors
- Soham Ghosh; Mohammad Ashraf Hossain Sadi
- Publisher
- arXiv preprint (Black & Veatch / University of Central Missouri)
- Year
- 2025
- Document number
- arXiv:2512.21295
- Document language
- English
- Source type
- Scientific
- Access
- Open licence (downloadable)
- Licence
- CC BY 4.0: share with attribution
- Licence evidence
- arxiv.org
Original licence note
arXiv record licence is http://creativecommons.org/licenses/by/4.0/ (checked via arXiv OAI-PMH)
Citation
Soham Ghosh; Mohammad Ashraf Hossain Sadi (2025). Enhancing Grid Resilience for Giga-Watt Scale Data Centers Using High Voltage Circuit Breaker Operated Braking Resistors. arXiv preprint (Black & Veatch / University of Central Missouri). arXiv:2512.21295. https://doi.org/10.48550/arXiv.2512.21295
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.