Forced Oscillations in Power Systems Induced by Data Centers Hosting AI Workloads

arXiv (author manuscript) · Jovan Krajacic, Georgia Pierrou et al.

A preprint that analytically examines how periodic load swings during AI training can excite poorly damped grid modes, which connection points are most critical, and how two synchronized data centres interact.

On this page

Overview

The study addresses the square-wave demand fluctuation that appears in large model training, when thousands of GPUs raise and lower their power draw together. Servers make up 60% to 90% of facility consumption, and the fluctuation can lie between 0.05 and 1 Hz with a magnitude of tens of MW. That range can coincide with electromechanical grid modes, and if a poorly damped mode is excited, the result is flicker, equipment disconnection or a blackout.

The method is an analytical transfer-function model, validated by time-domain simulation on three test systems: a four-bus network, a two-area network and a larger one. The data-centre model includes IT load, cooling load, UPS and the grid-connection converter. The authors classify instabilities as saddle-node bifurcations of the forced periodic response or impasse-surface encounters, distinguished through Floquet multipliers and the minimum singular value of the algebraic Jacobian.

The findings show that the weaker the grid (compared short-circuit levels are 3000, 2000 and 1000 MVA), the larger the voltage oscillation for the same load swing. For a large enough swing, even a small-signal stable system can move to unbounded oscillation. The worst-case forcing frequency drifts away from the modal frequency as the swing grows, so looking at the modal frequency alone is not sufficient.

The work is a preprint and provides an analysis framework for system operators. It places the parameters a data-centre owner can influence (duty cycle, swing magnitude, harmonic content, workload scheduling) next to the grid characteristics that decide the outcome (connection point, damping, strength). The results can support new rules on the maximum load fluctuation allowed at specific grid locations.

Key points

  1. Training-driven square-wave demand swings lie between 0.05 and 1 Hz and reach tens of MW; the study models a profile between 50% and 100% of rated load at 1.0 Hz.
  2. Servers account for 60% to 90% of facility electricity use; because server power-factor correction is assumed, the load is modelled at unity power factor as an active-power variation only.
  3. Grid strength is compared at 3000, 2000 and 1000 MVA; on the weaker grid the same swing produces larger voltage oscillation.
  4. For large enough swings a small-signal stable system can reach unbounded oscillation, and a jump phenomenon appears at the largest magnitude studied.
  5. Among the duty cycles tested, 50% gives the largest forced oscillation compared with 25% and 75%; harmonics beyond the fundamental can also drive large oscillations.
  6. Two synchronized data centres at critical buses in the same area nearly double the oscillation; a half-cycle offset reduces it to about 3% of the single-facility response.
  7. The magnitude of the transfer function identifies critical data-centre locations, and its phase decides whether several facilities reinforce or cancel each other.
  8. Workload scheduling emerges as a practical mitigation measure.

Using it in design

  • Before a connection request, obtain the expected load profile (magnitude, frequency range, duty cycle, harmonics) from the workload owner and present it to the grid operator in that form.
  • At a low short-circuit-power connection point, ask for an additional oscillation study and define the acceptable load-swing magnitude in the connection agreement.
  • If several facilities will connect to the same bus or area, add start-time synchronization and offset management to the operating procedure.
  • Check by simulation how far the UPS and grid-connection converter controls pass load swings to the grid in the oscillation frequency band.
  • Assess whether energy storage or load smoothing is needed for the design swing magnitude, based on the strength of the connection point.

Who should read it

Electrical designers planning data-centre grid connections, system engineers running grid studies, and operators drafting connection rules.

Document contents

  1. Introduction
  2. Data Center Load Profiles and Modeling
  3. Analysis of Data Center Load Impact
  4. Results (four-bus, two-area and large test systems)
  5. Conclusion

Publication details

Authors
Jovan Krajacic; Georgia Pierrou; Maitraya Desai; Gabriela Hug; Gustavo Valverde
Publisher
arXiv (author manuscript)
Year
2026
Document number
arXiv:2609.27698v1
Document language
English
Source type
Scientific
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Article-specific arXiv view-license link grants arXiv a non-exclusive distribution right; this is not general commercial redistribution permission.

Citation

Jovan Krajacic; Georgia Pierrou; Maitraya Desai; Gabriela Hug; Gustavo Valverde (2026). Forced Oscillations in Power Systems Induced by Data Centers Hosting AI Workloads. arXiv (author manuscript). arXiv:2609.27698v1. https://doi.org/10.48550/arXiv.2609.27698

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.