Guideline for Sustainable Development of Data Centre (MIDA, Malaysia)

Original title Guideline for Sustainable Development of Data Centre

Malaysian Investment Development Authority

Malaysia's MIDA guideline ties the DESAC tax incentive to declared design PUE, CUE and WUE: PUE of 1.4 or below for hyperscale, 1.6 to 1.7 or below for colocation, and WUE of 2.2 m3/MWh or lower.

On this page

Overview

The guideline links Malaysia's aim of being Southeast Asia's data-centre hub with sustainability and offers a framework consistent with its 2050 net-zero goal. It applies to tax-incentive applications under the Digital Ecosystem Acceleration (DESAC) scheme; applications received by MIDA until 31 December 2027 are subject to these conditions. Objectives are attracting investment, building capacity in energy-efficient design and operation, accelerating renewable or clean energy use and encouraging water-efficiency innovation.

Eligibility rests on three measures. PUE is declared per ISO/IEC 30134-2 as annual total energy over IT energy, with the design PUE limit set by data-centre category. CUE is annual CO2 emissions over IT energy under ISO/IEC 30134-8 and, for grid electricity, equals the grid emission factor times PUE; the default factor for purchased solar PV electricity is 0.046 kg CO2 eq/kWh. WUE is declared per ISO/IEC 30134-9.

On water, new centres should be located in areas with a water stress index below 0.8 (Peninsular Malaysia). The recommended design WUE is 2.2 m3/MWh or lower; the organisation monitors and discloses actual WUE in its annual sustainability report and works to reach 2.0 m3/MWh or lower from the baseline design value over the next 10 years. Appendix 1 gives PUE targets by category and Appendix 2 the 2021 grid emission factors (Peninsular 0.758, Sabah 0.425, Sarawak 0.198 Gg CO2/GWh).

Key points

  1. Incentive applications until 31 December 2027 are subject to this guideline (DESAC).
  2. PUE is declared as annual energy ratio per ISO/IEC 30134-2; the design PUE limit depends on category.
  3. Design PUE targets are 1.4 or below for hyperscale, 1.6 or below for newly built colocation and 1.7 or below for other colocation and enterprise categories; current baselines are to be validated.
  4. CUE = grid emission factor x PUE (ISO/IEC 30134-8); default factor for purchased PV electricity is 0.046 kg CO2 eq/kWh.
  5. Grid emission factors: Peninsular Malaysia 0.758, Sabah 0.425, Sarawak 0.198 Gg CO2/GWh.
  6. New facilities should be sited where the water stress index is below 0.8 (Peninsular Malaysia).
  7. The recommended design WUE is 2.2 m3/MWh or lower, with 2.0 m3/MWh or lower targeted within 10 years.
  8. Categories are split by power capacity: above 21.25 MW, 4.25 to 21.25 MW and 0.85 to 4.25 MW.

Using it in design

  • For a Malaysian incentive application, calculate and declare the design PUE to ISO/IEC 30134-2 against the category limit (1.4, 1.6 or 1.7).
  • For the CUE declaration, prepare an energy source table that accounts for the regional grid emission factor and any PV or diesel generator emissions.
  • Check the water stress index (below 0.8) in site selection; for water-cooled designs make the 2.2 m3/MWh WUE target a design criterion.
  • Include reclaimed or reused water in the water strategy and design meters to track actual WUE.
  • Write the application deadline (31 December 2027) into the project plan.

Who should read it

Investors, design consultants and operators in Malaysia designing data centres for the DESAC incentive and preparing sustainability reports.

Document contents

  1. Introduction
  2. Eligibility criteria (PUE, CUE, WUE)
  3. Effective date of application
  4. Appendix 1: Data centre categories and PUE and WUE targets
  5. Appendix 2: Grid emission factors

Publication details

Authors
Malaysian Investment Development Authority
Publisher
Malaysian Investment Development Authority
Year
Year not stated
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

No document publication date printed in inspected PDF; year remains null rather than inferred from URL folder.

Citation

Malaysian Investment Development Authority Guideline for Sustainable Development of Data Centre. Malaysian Investment Development Authority. https://www.mida.gov.my/wp-content/uploads/2024/12/Guideline-for-Sustainable-Development-of-Data-Centre.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.