White Paper: Characteristics and Risks of Emerging Large Loads (NERC Large Loads Task Force, July 2025)
North American Electric Reliability Corporation (NERC) · NERC Large Loads Task Force (LLTF), Reliability and Security Technical Committee (RSTC)
The first white paper of NERC's Large Loads Task Force; it defines large loads such as data centres, crypto mining and hydrogen production, characterises their electrical behaviour and ranks the risks they pose to the grid across planning, balancing, ride-through, voltage stability and power quality.
On this page
Overview
The white paper says computational, industrial and hydrogen production facilities are seeking to connect to the bulk power system faster than before and at a magnitude beyond the largest loads operating today. The Eastern and ERCOT Interconnections have each experienced a load-reduction event of roughly 1,500 MW of voltage-sensitive load. The Eastern event was mainly data centres and other power-electronic loads transferring to backup power and caused frequency overshoot and high voltage; in the ERCOT event, various loads reduced consumption during an extended low-voltage period in West Texas caused by a protection misoperation.
The large load definition rests not on a fixed MW threshold but on the ability to pose reliability risk (demand, operating characteristics and other factors); no MW threshold has yet been set. Existing practice is based on peak demand: in ERCOT, 75 MW or more is a large load, and NYISO studies loads of 10 MW or more at 115 kV and above and 80 MW or more below 115 kV. The paper stresses that peak demand is only one of many characteristics that affect reliability.
The characterisation chapter treats AI training facilities separately. In measured data from a 50 MW block of a 200 MW AI training site, demand changed at about 1.9 p.u. per second for about 250 ms when a training run started. Such rapid training and checkpoint ramps are observed in AI training but not in current AI inference workloads. An example is also given of a data centre ramping from about 450 MW down to about 40 MW in 36 seconds.
The risk chapter covers observability and data, long-term planning (demand forecasting, resource adequacy, transmission adequacy), operations and balancing, stability (ride-through, frequency, rotor angle, voltage, resonance and converter-driven stability, forced oscillations), power quality (harmonics, voltage fluctuations), security, load shedding and system restoration. The ride-through section recalls that some data centres switch to backup power after three transient voltage disturbances within one minute. The paper prioritises the risks and says a reliability gap analysis will follow.
Key points
- The Eastern and ERCOT Interconnections each saw a load-reduction event of roughly 1,500 MW of voltage-sensitive load.
- A large load is defined by its ability to pose reliability risk, not a fixed MW threshold; no MW threshold has been set yet.
- ERCOT treats 75 MW or more as a large load; NYISO studies 10 MW or more at 115 kV and above and 80 MW below 115 kV.
- In a 50 MW block of a 200 MW AI training site, demand changed at about 1.9 p.u. per second for about 250 ms when a training run started.
- Rapid training and checkpoint ramps are observed in AI training but not in current AI inference workloads.
- A data centre ramped from about 450 MW to about 40 MW in 36 seconds and then stayed near 7 MW for about 4 hours.
- Some data centres switch to backup power after three transient voltage disturbances within one minute.
- Risk topics: resource and transmission adequacy, balancing, ride-through, voltage stability, oscillations, voltage fluctuations, harmonics.
- A reliability gap analysis white paper will follow.
Using it in design
- In the grid-connection application, document ride-through behaviour (how many ms of voltage dip it stays connected for, backup transfer logic, return time).
- Treat AI training dP/dt (for example the ~1.9 p.u./s class) as a separate scenario in grid and generator studies; assess inference load separately.
- Disclose UPS transfer logic such as disturbance-counting schemes openly to the grid operator.
- The definition of a large load varies with the local threshold (for example 75 MW or 10 MW/80 MW); check which category the project falls into at the start of the connection process.
- Write load-shedding and reconnection ramp rates into the operating agreement; discuss scenarios like a sudden 450 MW to 40 MW drop with the balancing side.
Who should read it
Electrical engineers, grid planners and regulators planning grid connection, UPS transfer logic and AI load behaviour of large data centres.
Document contents
- Preface and executive summary
- Chapter 1: Introduction to large loads
- Chapter 2: Characterization of large loads
- Chapter 3: Risks to the bulk power system
- Chapter 4: Conclusion
- Appendix A: Large load construct data
- Appendix B: Comparison of characteristics and risks
Related standards
- IEEE 2800
- NERC PRC-024
Publication details
- Authors
- NERC Large Loads Task Force (LLTF); Reliability and Security Technical Committee (RSTC)
- Publisher
- North American Electric Reliability Corporation (NERC)
- Year
- 2025
- Document language
- English
- Source type
- Expert / community
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
NERC publication; no open licence stated in the document.
Citation
NERC Large Loads Task Force (LLTF); Reliability and Security Technical Committee (RSTC) (2025). White Paper: Characteristics and Risks of Emerging Large Loads (NERC Large Loads Task Force, July 2025). North American Electric Reliability Corporation (NERC). https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/3_doc_white-paper-characteristics-and-risks-of-emerging-large-loads.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.