The Role of the U.S. Electric Distribution System in Serving Data Center and Other Large Loads
National Laboratory of the Rockies / U.S. DOE · Gayathri Krishnamoorthy, Vincent Westfallen et al.
A 2026 U.S. national laboratory technical report on how data-centre growth affects distribution substations and feeders, interconnection processes and the mismatch in timelines.
On this page
Overview
The report examines data-centre connections from the distribution side, separately from generation and transmission bottlenecks. It defines the distribution system as the substation and feeder facilities that serve large loads, whether dedicated or shared with other customers. Using national datasets, utility filings and industry studies, it assesses demand growth, reliability requirements, interconnection thresholds and substation and feeder needs.
The core finding is a change of scale. Earlier developments were often small and connected to the mixed-use distribution system; the future pipeline is dominated by projects requesting 50 to 200 MW that need dedicated substations. Forecasts show data centres adding more than 155 GW of new demand in the coming years, more than tripling current operational capacity.
The second theme is timing. Data-centre construction and load ramps unfold within 12 to 24 months, while utility reinforcements take 3 to 5 years to plan, permit and deliver. The report discusses phased energization, temporary feeders, on-site generation and hosting capacity maps as ways to reduce that mismatch, along with structured interconnection frameworks.
Although the focus is data centres, the report notes that its insights apply to other high-density loads such as advanced manufacturing, hydrogen production and transport electrification. The utility structure it describes is American, but its treatment of reliability tiers, phased commissioning and interconnection thresholds offers a useful comparison for planning elsewhere.
Key points
- Data centres are forecast to add more than 155 GW of new demand in the coming years, more than tripling current operational capacity.
- The future pipeline is dominated by requests of 50 to 200 MW, which require dedicated substations.
- Nearly 15 GW of small and medium data centres are on mixed-use distribution feeders today; by 2030 about 9 GW more could join them, while 130 GW could drive the need for dedicated facilities.
- Meeting demand could require roughly 3,000 to 4,000 new feeders nationally and several thousand transformers in the 13 to 34.5 kV classes; most growth above about 50 to 75 MW will need hundreds of new substations.
- Data-centre buildout takes 12 to 24 months, while grid reinforcement takes 3 to 5 years.
- Uptime Institute tiers: Tier I provides basic capacity and Tier II adds redundant components; Tier III and IV often require redundant feeders and fault-tolerant substation configurations.
- When the grid cannot meet reliability thresholds, developers turn to front-of-meter and behind-the-meter batteries and backup generation.
- Hosting capacity maps for large loads should show area load-supporting capability, be updated more often and extend to higher voltage levels.
Using it in design
- Before filing a connection request, classify the demand size: above roughly 50 to 75 MW assume a dedicated substation and a long delivery time.
- Build the 3 to 5 year grid-reinforcement period into the project programme, and assess bridging by phased energization, temporary feeders or on-site generation at the first design stage.
- Clarify early with the utility the redundant-feeder and fault-tolerant substation requirement for the target Uptime Institute tier (Tier III and IV).
- If grid reliability is insufficient, include behind-the-meter batteries and backup generation in scope and assess their environmental permitting effects (diesel emissions, noise, water).
- Pre-screen candidate sites with hosting capacity maps and prioritize locations where grid capacity can be shared.
Who should read it
Developers and electrical designers selecting data-centre sites and planning grid connections, and utility distribution planning teams.
Document contents
- Executive Summary
- Introduction
- Data Center Landscape (functional categories and tiers, energy usage forecasts, existing and proposed data centers, redundancy requirements)
- Grid Interconnection Pathways (connection options, criteria and thresholds, bridging and flexible interconnection, reliability and redundancy)
- Distribution System Planning Processes and Considerations of Large Loads (forecast, substation and feeder impacts, power quality and operations)
- Permitting and Interconnection Process (hosting capacity and transparency tools, expansion timeline, illustrative process)
- Conclusion
Publication details
- Authors
- Gayathri Krishnamoorthy; Vincent Westfallen; Killian McKenna
- Publisher
- National Laboratory of the Rockies / U.S. DOE
- Year
- 2026
- Document number
- NLR/TP-6A40-96783
- Document language
- English
- Source type
- Scientific
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official 44-page PDF downloaded from OSTI. PDF p. 4 grants rights for U.S. Government purposes; it does not establish unrestricted commercial redistribution of this contractor-authored work.
Citation
Gayathri Krishnamoorthy; Vincent Westfallen; Killian McKenna (2026). The Role of the U.S. Electric Distribution System in Serving Data Center and Other Large Loads. National Laboratory of the Rockies / U.S. DOE. NLR/TP-6A40-96783. https://doi.org/10.2172/3364024
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.