Arc Fault Energy Reduction for Power Systems
Rehlko · Al deLeon (Rehlko)
A Rehlko technical paper that explains arc fault, arc flash and arc energy, the evolution of NEC 240.87 requirements, and methods of reducing energy at generator breakers.
On this page
Overview
The paper first separates the concepts. An arc fault is current flowing through an unintended path; between two phases or neutral and ground it is a parallel arc, along the same conductor a series arc. The discharged energy causes an arc flash. The magnitude depends on the current and the time before a protective device clears the fault, and it is thermal energy measured in kcal/cm². The aim is to reduce the magnitude of the fault current or its duration.
The safest approach is to eliminate the possibility of an arc flash, which is done by de-energising and lock-out tag-out (LOTO) procedures. Where energised work is unavoidable, breakers are set to open quickly. The paper also stresses that generators should not be running during maintenance.
NEC 240.87 was introduced in 2011 to require acceptable arc energy reduction methods where installations have little or no instantaneous trip protection. In 2014 the systems covered were defined and a requirement for overcurrent devices of 1200 A and above was added, and the 2017 and 2020 revisions brought in fused systems and current-limiting fuses. Accepted methods include zone selective interlocking (ZSI), differential relaying, an energy-reducing maintenance switch (ERMS), active arc flash mitigation, instantaneous trip setting and override, and approved equivalent means. The section also requires the method to be documented and the short-circuit and arc flash studies to be updated after major system changes.
On the generator side, breakers come with basic short-circuit protection; turning on an ERMS pulls the instantaneous pickup to a pre-programmed value and the breaker opens as fast as possible. The Rehlko APM603 on-board controller can also monitor short-circuit current and send a trip signal to the breaker, giving protection below the breaker's instantaneous trip without temporarily adjusting the breaker. The paper is product-oriented and recommends using the study results for labelling.
Key points
- Arc energy is thermal energy in kcal/cm², dependent on fault current and clearing time; reduction means lowering current or time.
- A parallel arc occurs between two phases or neutral-ground, a series arc along the same conductor.
- The primary measure is de-energised work and LOTO; the generator should not run during maintenance.
- NEC 240.87 was introduced in 2011; extended in 2014 to overcurrent devices of 1200 A and above; fused systems and current-limiting fuses were added in 2017 and 2020.
- Accepted methods: ZSI, differential relaying, energy-reducing maintenance switch, active arc flash mitigation, instantaneous trip setting and override, approved equivalent means.
- NEC 240.87 requires the method to be documented and studies updated after major system changes.
- With an ERMS on, the instantaneous pickup is pulled to a pre-programmed value and the breaker opens as fast as possible.
- The APM603 controller can monitor short-circuit current and send a breaker trip signal.
Using it in design
- When selecting the generator output breaker, decide the instantaneous protection and ERMS need from the site short-circuit and arc flash study.
- On breakers of 1200 A and above, name the NEC 240.87 method (ZSI, ERMS, active mitigation and so on) explicitly in the design and documents.
- Evaluate ERMS or controller-based tripping together with the coordination study; check coordination of the instantaneous setting with downstream devices.
- Add renewal of the short-circuit and arc flash study and the labels after major system changes to the commissioning and maintenance plan.
- Make generator shutdown and LOTO steps mandatory in maintenance procedures.
Who should read it
Electrical engineers designing generators and low-voltage distribution, and teams responsible for operational safety.
Document contents
- Introduction
- Definitions: arc fault, arc flash and arc energy
- Elimination or reduction of arc energy
- Arc energy reduction requirements (NEC)
- Short circuit and arc flash study
- Personal protective equipment
- Arc energy reduction in generator systems
- Summary
Related standards
- NFPA 70 (NEC) 240.87
- NFPA 70E
- IEEE 1584
Publication details
- Authors
- Al deLeon (Rehlko)
- Publisher
- Rehlko
- Year
- 2025
- Document number
- G26-59
- Document language
- English
- Source type
- Manufacturer
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Vendor white paper; no open licence. Year from PDF metadata (Dec 2025).
Citation
Al deLeon (Rehlko) (2025). Arc Fault Energy Reduction for Power Systems. Rehlko. G26-59. https://techcomm.rehlko.com/techcomm/pdf/Rehlko_G26-59_Arc_Fault_Energy_Reduction_for_Power_Systems_WP.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.
