Spirotech's November 2024 bulletin covers correct expansion vessel pre-pressure, placing the vessel on the return before the pump suction, water hardness classes (soft below 8.4 °dH) and vacuum degasser monitoring.
On this page
Overview
The document is Spirotech's 8-page November 2024 technical bulletin for installers and technicians. It has four topics: pressurisation, system water hardness, frequently asked questions and connection diagrams for pressurisation units. The text focuses on heating systems; the same principles apply to closed chilled water and glycol circuits.
The pressurisation section explains that a missing or wrongly sized expansion vessel causes boiler failure, safety valve discharge, frequent refilling and air entering the system. Vessel size depends on system water volume, static height above the vessel, boiler capacity (kW) and maximum temperature. If the gas pre-pressure is too low, usable volume shrinks and top points can go to negative pressure and draw in air; if too high, expansion water cannot enter the vessel and pressure may exceed the safety valve opening pressure. Per EN 12828 pre-pressure is set so that positive pressure remains at the highest point even when the vessel reserve is used up.
The vessel should be connected on the return, on the suction side of the circulation pump, so the pump gets stable suction pressure and no part of the system sees underpressure. At annual maintenance the vessel is disconnected and drained before pre-pressure is checked. In the hardness section, hardness below 1.5 mmol/l is soft (0 to 8.4 °dH), 1.5 to 2.5 mmol/l medium (8.4 to 14 °dH) and above 2.5 mmol/l hard (14 to 21 °dH); total hardness is 2.5[Ca2+] + 4.1[Mg2+]. Scale cuts heat transfer and wears pumps, valves and meters.
The FAQ covers why a pressure maintenance system is required under EN 12828, the data needed for design (total heat generator output, system volume, flow and return temperatures, static height, safety valve blow-off pressure, medium type, glycol percentage) and how vacuum degasser HMI data supports fault diagnosis.
Key points
- Expansion vessel gas pre-pressure must be set correctly: too low reduces usable volume and air is drawn in; too high stops expansion water entering the vessel and the safety valve may discharge water.
- Per EN 12828 pre-pressure is set so positive pressure remains at the highest point even when the vessel reserve is used up.
- The vessel belongs on the return, on the suction side of the circulation pump, giving stable suction pressure.
- Vessel sizing uses system water volume, static height, capacity (kW) and maximum temperature; EVN vessels range from 4 to 140 litres.
- At annual maintenance the vessel is disconnected and drained before pre-pressure is measured; a maintenance unit allows adjustment without removal.
- Water hardness: soft below 1.5 mmol/l (0 to 8.4 °dH), medium 1.5 to 2.5 mmol/l (8.4 to 14 °dH), hard above 2.5 mmol/l (14 to 21 °dH); total hardness = 2.5[Ca2+] + 4.1[Mg2+].
- Scale reduces heat transfer, raises energy cost and wears pumps, valves and meters; temporary hardness drops on boiling, permanent hardness needs a softener.
- Vacuum degasser run-time trends can point to air entry, a faulty automatic air vent, a wrongly set vessel or a leak; the unit stops if no gas is detected over 10 minutes and retries at 08:00 next day.
Using it in design
- On closed chilled water and glycol circuits, size the expansion vessel to system volume, static height, temperature range and glycol percentage.
- Connect the vessel on the return before the pump suction and set pre-pressure so positive pressure remains at the highest point.
- Specify water hardness and quality; evaluate softening or treatment where hard water is used.
- Feed the vacuum degasser run time into monitoring and alarm on sudden increases as a sign of air entry or leaks.
- Add annual pre-pressure checks to the maintenance plan; consider a maintenance unit for checks without removing the vessel.
Who should read it
Plant and hydronic engineers and technicians designing pressurisation, water quality and operation of heating and chilled water circuits.
Document contents
- 1. Taking the stress out of pressurisation
- 2. System water quality: hardness
- 3. Frequently asked questions
- 4. Connection diagrams for pressurisation units
Publication details
- Authors
- Spirotech
- Publisher
- Spirotech
- Year
- 2024
- Document number
- Edition November 2024
- Document language
- English
- Source type
- Manufacturer
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official public manufacturer source inspected. No redistribution permission established. Metadata and original brief summaries only; local files are research evidence, not a redistribution package.
Citation
Spirotech (2024). Technical Bulletin: Technical Information for Installers and Technicians: Edition November 2024. Spirotech. Edition November 2024. https://www.spirotechportal.com/da/4d284e49-9796-4e4e-9526-b891e4ce1c8d
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.