Research paperPDF2019

Thermal Performance Evaluation of a Data Center Cooling System under Fault Conditions

Energies (MDPI AG) · Jinkyun Cho, Beungyong Park et al.

A case study of a 20 MW, nine-storey chilled-water CRAH data centre in Korea with cold-aisle containment and district cooling: after the central plant stops and UPS-backed pumps keep circulating, how long can the thermal capacity of the water in the pipes keep server inlets within ASHRAE limits?

CC BY 4.0 — share with attribution

On this page

Overview

The study asks how long server inlet temperature stays acceptable during a cooling system fault and how quickly backup cooling must be running. The 6SigmaDC room model has 192 racks at 4.0 kW with CAC, underfloor supply with side-wall return, a 900 mm raised floor, a 3.0 m false ceiling, 150 kW CRAHs and chilled water varied from 10 to 18 °C. The model finds the highest chilled-water and CRAH supply temperatures that still give compliant inlets, and a pipe-volume energy balance then converts those temperatures into elapsed time after the outage.

Server inlets stayed within 18-27 °C up to a CRAH supply-air temperature of about 24 °C, corresponding to 17 °C chilled water. Above 17 °C chilled water, CRAH capacity falls below 80% and room temperature rises rapidly; from 18 °C chilled water and 25 °C supply air, coil capacity fell below the load and inlet temperatures rose rapidly. The chilled-water piping held 234.3 m³ in total, about 45 m³ per typical floor, serving a 2500 kW floor cooling load at 6.75 m³/min with a fixed 5.5 °C water delta-T.

After the outage, chilled water took about 150 s to rise from 10 to 14 °C, and the whole 45 m³ reached 15.5 °C at 3.45 min, 21.0 °C at 10.36 min and 26.5 °C at 17.27 min. Compliant operation could continue for about 320 s (5 min 20 s) after the cooling outage, with CRAH coil capacity at 85%, so backup cooling must be active within 300 s. High-temperature, contained designs have only about five minutes before backup cooling must be running.

Limits: a single project (20 MW, Korea) and six fault conditions; the result depends on this plant's pipe volume, CRAH capacity and 4 kW per rack load. The authors also address organising and managing operational stability and energy-efficiency verification systematically through the commissioning process.

Key points

  1. CFD module: 192 racks at 4.0 kW/rack with CAC, underfloor supply with side-wall return, 900 mm raised floor, 3.0 m false ceiling, 150 kW CRAHs and chilled water from 10 to 18 °C.
  2. Server inlets stayed within 18-27 °C up to a CRAH supply-air temperature of about 24 °C, corresponding to 17 °C chilled water; above that CRAH capacity falls below 80% and room temperature rises rapidly.
  3. The chilled-water piping held 234.3 m³ in total, about 45 m³ per typical floor, serving a 2500 kW floor cooling load at 6.75 m³/min with a fixed 5.5 °C delta-T.
  4. After the outage, water took about 150 s to rise from 10 to 14 °C; the 45 m³ reached 15.5 °C at 3.45 min, 21.0 °C at 10.36 min and 26.5 °C at 17.27 min.
  5. Compliant operation could continue for about 320 s (5 min 20 s) after the outage with CRAH coil capacity at 85%, so backup cooling must be active within 300 s.
  6. From 18 °C chilled water and 25 °C supply air, coil capacity fell below the load and inlet temperatures rose rapidly.

Using it in design

  • Calculate the permissible time for a cooling outage with a pipe-volume energy balance and set the backup-cooling start time accordingly (here 300 s); high-temperature, contained designs give less time.
  • Limit chilled-water and CRAH supply temperature to the ASHRAE-compliant upper bound (17 °C water, 24 °C air) as the pre-fault operating point; above 17 °C capacity falls below 80%.
  • Model UPS-backed pumps and pipe volume (45 m³ per typical floor) as thermal buffer and add them to fault-condition commissioning test scenarios.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Check cooling capacity alongside your design

Review zone heat loads, available capacity and the capacity balance after the largest unit is lost in SoSo CAD.

Request a demo
Zone heat loads and capacity balance in the SoSo CAD cooling workspace

Who should read it

Designers and commissioning engineers determining cooling fault resilience and backup-cooling start time.

Document contents

  1. 1. Introduction
  2. 2. Literature Reviews
  3. 3. Major Issues in Data Center Planning (3.1 Root Causes and Scale of Fault Conditions, 3.2 Temperature and IT Reliability)
  4. 4. Case Study: Data Center and Modeling (4.1 Data Center Cooling System, 4.2 IT Server Room Thermal Model, 4.3 Simulation)
  5. 5. Temperature Control Approaches (5.1 Temperature Increase over Time After a Cooling System Outage)
  6. 6. Conclusions

Related standards

  • ASHRAE TC 9.9 Thermal Guidelines for Data Processing Environments
  • Uptime Institute Tier Standard

Read the document

dc-cooling-outage-fault-conditions-2019.pdf

PDF · 8.1 MB · English

CC BY 4.0 — share with attribution

The document is provided unaltered because its licence permits redistribution.

Publication details

Authors
Jinkyun Cho; Beungyong Park; Yongdae Jeong
Publisher
Energies (MDPI AG)
Year
2019
Volume
12
Issue
15
Pages
2996
Document language
English
Source type
Scientific
Access
Open licence — downloadable
Licence
CC BY 4.0 — share with attribution
Licence evidence
www.mdpi.com
Original licence note

PDF p.1: open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.

Citation

Jinkyun Cho; Beungyong Park; Yongdae Jeong (2019). Thermal Performance Evaluation of a Data Center Cooling System under Fault Conditions. Energies (MDPI AG). 12(15), 2996. https://doi.org/10.3390/en12152996

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.