White paperFree to read2022

Next-Generation Data Center Facility White Paper

Huawei Digital Power

Developed by Huawei with industry experts, the paper defines a next-generation facility by four attributes: sustainable, simplified, autonomous-driving (automated O&M) and reliable. It argues for moving from PUE alone to a family of xUE metrics.

On this page

Overview

According to the paper, PUE of global large data centres stayed around 1.6 for seven years (Uptime 2021), while Chinese policy targets new large data centres below 1.3 by 2025. The authors therefore advise looking beyond PUE to CUE, WUE and other xUE metrics, heat reuse and recyclability.

On speed and space, prefabricated modular build can cut a 1000-rack data centre from more than 18 months to 6-9 months. In one cited project the PowerPOD reference saves more than 40 % of power-system space, allowing 350 more IT racks and more than 16,000 m less power cable. Above about 20 kW per rack, liquid cooling is expected to become the primary method with air as auxiliary (converged air-liquid cooling).

The operations and reliability section rests on automation. A 1000-rack data centre typically needs 15-30 O&M engineers doing 6-12 on-site inspections, while infrared and robotic inspection covers 2000 racks remotely in 5 minutes. AI energy optimisation at Huawei Cloud Langfang (700+ points) cut annual PUE from 1.42 to 1.25, saving 33.36 GWh. Per Uptime 2021, power and cooling failures account for 57 % of outages (43 % power, 14 % cooling).

Key points

  1. PUE of large DCs stayed around 1.6 for seven years (Uptime 2021); Chinese policy targets new large DCs below 1.3 by 2025.
  2. Prefabricated modular build cuts a 1000-rack DC from more than 18 months to 6-9 months.
  3. PowerPOD reference saved >40 % of power-system space: 350 more IT racks and >16,000 m less power cable.
  4. Above about 20 kW per rack liquid cooling becomes primary, with air as auxiliary.
  5. A 1000-rack DC needs 15-30 O&M engineers and 6-12 on-site inspections; robotic inspection covers 2000 racks in 5 minutes.
  6. Huawei Cloud Langfang AI optimisation cut annual PUE from 1.42 to 1.25, saving 33.36 GWh.
  7. Uptime 2021: 57 % of outages come from power and cooling (43 % power, 14 % cooling).

Using it in design

  • Support CUE, WUE and a heat-reuse fraction next to PUE in reports.
  • In the cooling advisor, suggest liquid cooling above about 20 kW per rack.
  • In ops planning, estimate O&M headcount from rack count and automation level.
  • In reliability checks, weight power-chain design heavily, since power causes the largest outage share.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Compare the cost of design decisions

Evaluate equipment costs, energy expenses and total cost of ownership (TCO) using your inputs and assumptions in SoSo CAD.

Request a demo
CAPEX and TCO estimates in the SoSo CAD cost workspace

Who should read it

Facility investors and designers planning metrics, operations and fast deployment together.

Related standards

  • GB 50174-2017
  • The Green Grid xUE metrics

Publication details

Authors
Huawei Digital Power
Publisher
Huawei Digital Power
Year
2022
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Huawei Digital Power (2022). Next-Generation Data Center Facility White Paper. Huawei Digital Power. https://digitalpower.huawei.com/attachments/index/1c651408309b41c78e368a270f89d89e.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.