The Green Grid's 2011 white paper examines containerised and modular data centre facilities (CMDF) as pre-engineered, prefabricated building blocks.
On this page
Overview
WP#42 is a Green Grid white paper dated 15 November 2011, edited by Christopher Kelley (Cisco) and Jud Cooley (Oracle), with Ron Bednar, Buster Long and Suzen Shaw among the authors.
The white paper examines containerised and modular data centre facilities (CMDF). They are described as repeatable, pre-engineered, prefabricated and quality-assured building blocks. The approach means thinking of a data centre not as a single structure built on site but as a set of modules prepared in a factory and brought to the site.
The abstract lists the expected benefits: rapid deployment, lower operating and capital cost, and higher density. The paper also notes that multiple implementation approaches exist across suppliers, so CMDF is a category covering different architectures rather than a single product type. Limits: the paper dates from 2011 and its full text was not read, so capacity ranges, cost comparisons and implementation details are absent from this record. For designers its value is in supporting the treatment of prefabricated modules in design tools as catalogue items with fixed capacity, footprint and interfaces.
Key points
- Dated 15 November 2011; editors Christopher Kelley (Cisco) and Jud Cooley (Oracle).
- CMDF are repeatable, pre-engineered, prefabricated and quality-assured building blocks.
- Expected benefits: rapid deployment, lower operating and capital cost, higher density.
- Multiple implementation approaches exist across suppliers.
- The author group also includes Ron Bednar, Buster Long and Suzen Shaw.
Using it in design
- Support prefabricated module objects (power skids, container halls) as catalogue items with fixed capacity, footprint and interfaces.
- State supplier-specific implementation differences explicitly in the module definition.
- Plan the need for rapid deployment together with site preparation work (ground, utility connection).
- Verify cost and density claims against supplier data; this record only states expected benefits.
Monthly newsletter · free
Keep your reading list current
Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.
SoSo CAD
Check cooling capacity alongside your design
Review zone heat loads, available capacity and the capacity balance after the largest unit is lost in SoSo CAD.
Request a demo
Who should read it
Designers, owners and procurement teams planning data centre capacity for rapid deployment.
Publication details
- Authors
- Christopher Kelley; Jud Cooley; Ron Bednar; Buster Long; Suzen Shaw
- Publisher
- The Green Grid
- Year
- 2011
- Document number
- WP 42
- Document language
- English
- Source type
- Industry body
- Access
- Citation only
- Licence
- Copyright retained; citation only — the publisher’s terms apply to the original document
Original licence note
Download requires a free TGG account sign-in and is governed by The Green Grid Terms of Use; summary and facts from the public library landing page; full text not redistributed.
Citation
Christopher Kelley; Jud Cooley; Ron Bednar; Buster Long; Suzen Shaw (2011). WP#42 - Deploying and Using Containerized Modular Data Center Facilities. The Green Grid. WP 42. https://www.thegreengrid.org/en/resources/library-and-tools/388-WP%23-42---Deploying-and-Using-Containerized-Modular-Data-Center-Facilities
Events on this subject
Browse the events calendarAll content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.