Is PUE actually going UP?
Uptime Institute Journal (Uptime Institute) · A. Lawrence
A. Lawrence's Uptime Institute Journal article discusses the 2019 survey finding that average PUE rose from 1.58 to 1.67, and the possible reasons.
On this page
Overview
The article starts from the finding of the 2019 Uptime Institute survey that average PUE rose from 1.58 in 2018 to 1.67 in 2019. The sample covered 624 sites. The author asks whether the rise reflects a real loss of efficiency or a measurement and sampling effect, and lists possible explanations. The article should be read as a short, open-ended assessment that questions how averages of a widely accepted industry metric should be interpreted.
The suggested causes include hotter weather, lower utilisation and higher power density. The piece stresses that these factors were not measured individually, so the exact cause of the rise is unknown; the text is therefore commentary rather than proof. In other words, the rise has not been separated by cause with data, so the results should be treated as a list of factors to watch rather than as a firm cause-and-effect relationship in design decisions.
The most important distinction in the article is between average PUE per site and overall PUE per kW of IT load. As work shifts to cloud and large colocation facilities, the site average can rise while the load-weighted overall PUE falls. The author also notes that PUE is not the only efficiency metric and cautions against reading it in isolation.
As context, hyperscale and large colocation operators claim annual or design PUE between 1.1 and 1.4. The largest efficiency gains are described as having come between 2007 and 2013 from hot/cold separation, higher temperatures and cooling controls, after which progress slowed. The declared low values should therefore be read as the results of large facilities with particular operating conditions, not as a target every sector average could reach.
Key points
- Average PUE rose from 1.58 in 2018 to 1.67 in 2019 (sample of 624).
- Hyperscale and big colo operators claim annual or design PUE between 1.1 and 1.4.
- The largest efficiency gains came in 2007-2013 from hot/cold separation, higher temperatures and cooling controls.
- Possible causes include hotter weather, lower utilisation and higher density.
- Average PUE per site is not the same as overall PUE per kW of IT load.
- Load-weighted overall PUE is falling as work moves to cloud and large colos.
- PUE is not the only efficiency metric and should not be read alone.
Using it in design
- In a PUE benchmark display, show the survey average next to the hyperscale range.
- State clearly that a site-average PUE is not load-weighted.
- When setting a design PUE target, treat utilisation and seasonal temperature effects as separate scenarios.
- Present PUE together with complementary metrics in efficiency reports.
- Treat hot/cold separation, higher operating temperature and cooling controls as proven sources of PUE improvement.
Monthly newsletter · free
Keep your reading list current
Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.
SoSo CAD
Compare the cost of design decisions
Evaluate equipment costs, energy expenses and total cost of ownership (TCO) using your inputs and assumptions in SoSo CAD.
Request a demo
Who should read it
Data center designers and energy managers who set efficiency targets or interpret PUE data.
Publication details
- Authors
- A. Lawrence
- Publisher
- Uptime Institute Journal (Uptime Institute)
- Year
- 2019
- Document language
- English
- Source type
- Industry body
- Access
- Free to read
- Licence
- Copyright retained; citation only — the publisher’s terms apply to the original document
Original licence note
Uptime Institute Journal article, copyright Uptime Institute, no open licence. Citation only.
Citation
A. Lawrence (2019). Is PUE actually going UP?. Uptime Institute Journal (Uptime Institute). https://journal.uptimeinstitute.com/is-pue-actually-going-up/
Events on this subject
- iMasons Climate Accord Summit
- Data Center World Middle East
- ELECO 2026 Elektrik-Elektronik ve Biyomedikal Mühendisliği Konferansı
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.