¿Cómo instalar un Data Center en Chile?
Ministerio de Ciencia, Tecnología, Conocimiento e Innovación, Chile
Chile's Ministry of Science guide (June 2025) lists energy feasibility, land use and permits for data-centre installation: environmental declaration (DIA) 12-18 months, building permit 6-8 months, archaeological permit about 18 months.
On this page
Overview
The guide was published by MinCiencia in June 2025 under Chile's National Data Centre Plan (PDATA) as a reference to ease installation. After a section promoting Chile for clean energy, connectivity and a stable investment climate, it gives practical recommendations built from industry-reported obstacles.
Promotional data include: 66.1% of electricity generation from renewables in early 2024 (40.7% non-conventional, 25.4% conventional hydro), non-conventional renewable capacity above 14,800 MW (solar 9,031 MW, wind 4,517 MW), over 62,000 km of fibre, and more than US$2.3 billion of data-centre projects delivered in 2020-2024. Over 30 projects are at various stages, with further investment estimated above US$4 billion.
Recommendations fall under five headings: energy feasibility (sites with substations that have capacity or near transmission lines, early coordination with the National Electric Coordinator, and Decree 38 requiring Tier IV generators from late 2025), land use and industrial classification (data centres count as energy infrastructure and as a nuisance industry), permits, inter-agency coordination and sustainability.
The document is not a design standard; it is a guide for planning the permit path and schedule. Suggested stages are preliminary assessment (2-3 months), base permit applications (6-18 months) and construction permits (6-12 months). For investments of US$100 million or more the Ministry of Economy acts as coordinator.
Key points
- 66.1% of electricity generation was renewable in early 2024: 40.7% non-conventional and 25.4% hydro; at least 80% is targeted by 2030.
- Non-conventional renewable capacity exceeds 14,800 MW (solar 9,031 MW, wind 4,517 MW); over 7,300 MW of new renewable projects are under construction or testing.
- The Environmental Impact Declaration (DIA) typically takes 12-18 months; the building permit (DOM) 6-8 months; the archaeological prospecting permit about 18 months on average.
- Data centres are classed as energy infrastructure and as a nuisance industry, mainly because of combustion generators.
- Decree 38 (2020) takes effect in late 2025 and requires stricter generator emission standards (Tier IV); buying equipment early is recommended.
- Rural or agricultural land needs a land-use change before the SAG.
- Suggested process: preliminary assessment 2-3 months, base permits 6-18 months, construction permits 6-12 months; the Ministry of Economy coordinates projects of US$100 million or more.
- Low-water cooling such as air cooling or water recycling, and 100% renewable supply through PPAs or RECs, are recommended.
Using it in design
- Treat a substation with available capacity or proximity to transmission lines as a siting precondition, and write to the National Electric Coordinator early.
- Specify generators to Tier IV emission levels and add the supply lead time to the programme.
- Build the schedule with DIA 12-18 months, DOM 6-8 months and, where needed, 18 months for the archaeological permit running in parallel.
- Start the cooling concept from low-water options (air cooling, water recycling) and present these commitments clearly in the DIA file.
Who should read it
Investors, permitting consultants and design teams planning data centres in Chile.
Document contents
- Why Chile is ideal
- Governance and strategic vision
- Clean and expanding energy
- Digital connectivity
- Growing digital ecosystem
- Government recommendations: energy, land, permits, coordination, sustainability
- Crucial stages of the process
Publication details
- Authors
- Ministerio de Ciencia, Tecnología, Conocimiento e Innovación, Chile
- Publisher
- Ministerio de Ciencia, Tecnología, Conocimiento e Innovación, Chile
- Year
- 2025
- Document language
- Spanish
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official PDF downloaded and extracted with pdftotext after web/TinyFish failures. Copyright page states first edition June 2025; September upload date is not the edition date.
Citation
Ministerio de Ciencia, Tecnología, Conocimiento e Innovación, Chile (2025). ¿Cómo instalar un Data Center en Chile?. Ministerio de Ciencia, Tecnología, Conocimiento e Innovación, Chile. https://minciencia.gob.cl/uploads/filer_public/39/e1/39e1511a-ddf8-4faf-8c7d-7b196cd17d92/guia-_pdata.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.
