Commissioning on-site electrical systems
Consulting-Specifying Engineer · Kenneth Kutsmeda
Kutsmeda adapts ASHRAE Guideline 0's four-phase commissioning process to on-site electrical systems in critical facilities and argues that commissioning must begin in pre-design.
On this page
Overview
Kutsmeda's article adapts ASHRAE Guideline 0's four-phase commissioning process to on-site electrical systems in critical facilities. His central argument is that commissioning must begin in pre-design so that the design supports testing. The article lays out the equipment scope and three test levels: individual equipment, discrete system and integrated system (black-start).
The discrete system level means, for example, testing PDU, UPS and switchgear together under load and on generator. The integrated level covers site-wide black-start with partial failures. The design phase should provide load-bank connections or isolation breakers for phased construction, and control sequences with timer presets for every mode.
In the construction phase, the article notes that factory tests often miss interfaces with controls, mechanical and life-safety systems, so the commissioning authority (CxA) may add witnessed procedures. In a North Carolina data centre case study, a manufacturer-built simulator and phased testing uncovered defective breakers, failure-mode interaction problems and inrush coordination issues.
The commissioned system later rode through a 25 kV utility switch fault without losing critical load; the owner estimated a recovery cost of $5 million had it dropped. The limits of the article are that it rests on a single 2008 case study and that the cost figure is the owner's own estimate. Related documents named are ASHRAE Guideline 0-2005, NETA ATS, IEEE 450, IEEE 1188, NFPA 70E, NFPA 110 and NFPA 111.
Key points
- Three test levels: individual equipment, discrete system (e.g., PDU+UPS+switchgear under load and on generator) and integrated site-wide black-start with partial failures.
- The design phase must provide load-bank connections or isolation breakers for phased construction, and control sequences with timer presets for every mode.
- Factory tests often miss interfaces with controls, mechanical and life-safety systems; the CxA may add witnessed procedures.
- Case study testing found defective breakers, failure-mode interaction problems and inrush coordination issues.
- A post-commissioning 25 kV utility switch fault was ridden through without losing critical load.
- The owner estimated a $5 million recovery cost had the load dropped.
Using it in design
- Plan load-bank connection points and isolation breakers for phased construction. Separate component, discrete-system and integrated tests in the commissioning schedule.
- Record the sequence-of-operations timer settings for transfer and paralleling equipment.
- Involve the commissioning authority from the earliest design stage.
- Define witnessed site tests for interfaces that factory tests do not cover.
Who should read it
Engineers and commissioning authorities who design, commission and test electrical systems for critical facilities.
Related standards
- ASHRAE Guideline 0-2005
- NETA ATS
- IEEE 450
- IEEE 1188
- NFPA 70E
- NFPA 110
- NFPA 111
Publication details
- Authors
- Kenneth Kutsmeda
- Publisher
- Consulting-Specifying Engineer
- Year
- 2008
- Document language
- English
- Source type
- Expert / community
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Citation
Kenneth Kutsmeda (2008). Commissioning on-site electrical systems. Consulting-Specifying Engineer. https://www.csemag.com/articles/commissioning-on-site-electrical-systems/
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.
