Technical requirements for large demand facilities (Suurten kulutuslaitosten tekniset vaatimukset), Fingrid
Original title Suurten kulutuslaitosten tekniset vaatimukset
Fingrid Oyj
Fingrid's technical requirements for large demand facilities (for example large data centres) with a rated demand of at least 30 MW that connect directly to Finland's transmission system. The document complements KJV2018 and must be distinguished from the KJV2026 consultation draft. It is the first version, dated 12 June 2026.
On this page
Overview
The document contains the requirements Fingrid has set, under its system responsibility, for demand facilities with a rated demand of at least 30 MW connected to the transmission network. Distribution networks and facilities connected to them are excluded. The requirements apply to new facilities and to existing ones when their technical characteristics are changed or equipment is added; for energy storage only the pumping units of pumped-storage plants are covered, and other storage falls under separate system technical requirements (SJV). The aim is that the facility withstands voltage and frequency variations, does not disconnect from normal variations, does not harm other equipment, and that Fingrid has the information it needs for system planning.
The process section defines verification of requirements and the notification procedure in phases: Phase 0 (pre-design), Phase 1 (design, connection notification EON and interim operational notification ION), Phase 2 (commissioning and verification) and Phase 3 (inspection and approval, final operational notification FON). Fingrid assesses the need for special studies (subsynchronous interaction, geomagnetically induced currents, damping of power oscillations, low minimum short-circuit power, converter interactions, dependence on other equipment, power quality and the need for dynamic voltage control) in pre-design, before the connection agreement is signed and before a binding purchase contract for main components, because such studies can affect equipment selection, sizing and schedule.
Among the technical requirements these stand out: continued normal operation at a rate of change of frequency below 2.0 Hz/s (one-second average), with no use of rate-of-change-of-frequency protection for protection; no disconnection for a permanent voltage angle change of up to +/-30 degrees; controlled limiting of active power consumption (the indicative adjustable range for the ramp rate is 5-50 MW/min); a rapid active power limiting function (at least 30% reduction, activating within one second of the control signal and reaching the setpoint in at most 15 minutes); automatic rapid limiting at undervoltage; fault ride-through, meaning no disconnection for eight 100 ms three-phase faults within a 90-second period; and recovery of active power to at least 90% within one second after voltage returns to 0.90 pu.
The document also sets permitted peak values for cyclic power oscillations by frequency band (for example 20% of rated demand, at most 40 MW, in the 0.01-0.025 Hz band), assessed at the connection point by spectral analysis, with additional equipment such as an energy-storage STATCOM required if needed. Power quality, continuous recording (instrumentation) and modelling requirements, the compliance plan, reports on voltage-disturbance withstand and power recovery, interaction and power controllability, equipment type tests and commissioning tests make up the compliance-verification section. It also contains a data submission and documentation list, exceptions, and real-time measurements and data exchange.
Key points
- Scope: new demand facilities connecting to Finland's transmission system with a rated demand of at least 30 MW (also applied to existing facilities when changed or expanded); distribution networks are excluded.
- The document complements and clarifies KJV2018; the first version is dated 12.6.2026.
- Process phases: Phase 0 pre-design, Phase 1 design (EON and ION), Phase 2 commissioning and verification, Phase 3 inspection and approval (FON).
- The need for special studies is assessed before the connection agreement and before binding main-component purchases; topics include subsynchronous interaction, low short-circuit power and converter interactions.
- Normal operation must continue at a rate of change of frequency below 2.0 Hz/s; rate-of-change-of-frequency protection is not used for this.
- Rapid active power limiting: at least 30% reduction, activation within 1 second of the control signal, reaching the setpoint in at most 15 minutes.
- Fault ride-through: no disconnection for eight 100 ms three-phase faults in a 90-second period; active power back to at least 90% within 1 second after voltage returns to 0.90 pu.
- Voltage angle change of up to +/-30 degrees must not cause disconnection; above +/-20 degrees demand may disconnect but active power must recover to at least 90% within 1 second.
- Cyclic power oscillation limit example: 20% of rated demand and at most 40 MW in the 0.01-0.025 Hz band (300 s spectral analysis window).
- The facility needs a continuous recording system for voltages, currents, active and reactive power and frequency at the connection point (power and frequency recorded at 50 Hz or faster).
Using it in design
- For a data-centre connection above 30 MW, discuss the need for special studies with Fingrid at pre-design and before main-component purchase; analyse early how UPS, converters and loads behave under subsynchronous interaction and low short-circuit power.
- Reflect the facility's voltage-disturbance and recovery behaviour (FRT, active power recovery) in UPS and converter selection; ask suppliers for documented evidence against the eight-fault sequence and the 90%-within-1-second recovery.
- Add control that can reduce active power quickly to a setpoint (30% limiting, activation within 1 second) and its control interface to the design; plan for the possibility that high load ramp rates must be limited.
- Assess cyclic power oscillations (such as AI training loads) against the limits in the given frequency bands and, where needed, reserve budget and space for an energy-storage STATCOM or battery system.
- Put the compliance-verification plan (model data, type tests, commissioning tests and the recording system) into the project and commissioning schedule; track Phases 0-3 and the EON, ION and FON notifications as milestones.
Who should read it
Electrical designers and grid-connection engineers connecting data centres or large demand facilities above 30 MW in Finland, UPS and converter manufacturers and commissioning teams.
Document contents
- Introduction
- Scope
- Terms and definitions
- Special study requirements for demand facilities
- Verification process for facility requirements and operational notification procedure (Phases 0-3, EON, ION, FON)
- Documenting and submitting electrical equipment data
- Exceptions to the requirements
- Real-time measurements and data exchange
- Requirements for demand facilities (rate of change of frequency, short-circuit power, voltage angle changes, supply change-over, autonomous connection, control and remote operation, active power control, rapid limiting, fault ride-through, active power recovery, reactive power compensation, interaction phenomena, power quality, instrumentation, modelling)
- Verification of compliance (compliance plan, reports, equipment type tests, commissioning tests)
Publication details
- Authors
- Fingrid Oyj
- Publisher
- Fingrid Oyj
- Year
- 2026
- Document number
- 12.6.2026
- Document language
- Finnish
- Source type
- Industry body
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Public official source inspected; no document-specific commercial redistribution permission established. Original short summaries and metadata only; downloads are local research evidence.
Citation
Fingrid Oyj (2026). Suurten kulutuslaitosten tekniset vaatimukset. Fingrid Oyj. 12.6.2026. https://www.fingrid.fi/globalassets/dokumentit/fi/palvelut/kulutuksen-ja-tuotannon-liittaminen-kantaverkkoon/fingrid---suurten-kulutuslaitosten-tekniset-vaatimukset.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.