Elektrik Üretim ve Elektrik Depolama Tesisleri Kabul Yönetmeliği

T.C. Enerji ve Tabii Kaynaklar Bakanlığı · Enerji ve Tabii Kaynaklar Bakanlığı

Ministry of Energy regulation on acceptance (kabul) of electricity generation and storage facilities and their operating-period obligations.

On this page

Overview

Acceptance authority lies with the Ministry or authorised bodies (POB); a committee chaired by a POB engineer with system-operator engineers inspects the site and may repeat site tests; tight review and reporting deadlines apply. Relevant when a data centre adds grid-connected PV or battery storage.

Related standards

  • Elektrik Tesisleri Proje Yönetmeliği
  • Elektrik Piyasasında Depolama Faaliyetleri Yönetmeliği
  • Elektrik Piyasasında Lisanssız Elektrik Üretim Yönetmeliği

Publication details

Authors
Enerji ve Tabii Kaynaklar Bakanlığı
Publisher
T.C. Enerji ve Tabii Kaynaklar Bakanlığı
Year
2020
Document number
RG 31044 (19.02.2020)
Document language
Turkish
Source type
Turkish regulation
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Licence evidence
www.mevzuat.gov.tr
Original licence note

Official Turkish legislation published in the Resmî Gazete; FSEK (Law 5846) Art. 31 allows laws and regulations to be reproduced freely.

Citation

Enerji ve Tabii Kaynaklar Bakanlığı (2020). Elektrik Üretim ve Elektrik Depolama Tesisleri Kabul Yönetmeliği. T.C. Enerji ve Tabii Kaynaklar Bakanlığı. RG 31044 (19.02.2020). https://www.resmigazete.gov.tr/eskiler/2020/02/20200219-1.htm

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.