Guide d'accompagnement: Implantation de centres de données
Original title Guide d’accompagnement: Implantation de centres de données
Direction générale des Entreprises
France's DGE guide (November 2025) helps local authorities and project owners site data centres: grid connection takes 2-3 to 6-9 years, large projects average 50-250 MW, and operations create about 50 jobs per 100 MW.
On this page
Overview
The guide is part of the DGE and Business France support effort for data-centre siting in France, and addresses local authorities, landowners and project owners. It defines enterprise, colocation, cloud, edge and high-density HPC/AI data centres, then makes the case for France through digital sovereignty, local tax revenue and low-carbon electricity. It cites 109 billion euros of investment announced at the AI summit and 63 suitable sites announced at Choose France 2025.
The siting section lists three core parameters: land, grid connection and infrastructure. Land needs range from a few hundred m² for edge to tens of hectares for hyperscale. Power ranges from a few MW for small sites to GW scale, averaging 50-250 MW for larger projects; above 40 MW an HTB high-voltage connection is required. Connection times vary from 2-3 years to 6-9 years, and the Île-de-France transmission grid is saturated.
The environmental section tabulates ideal features by territory type (temperate, water-stressed, humid, hot and cold). It suggests dry air cooling in water-stressed areas, indirect closed-loop evaporative cooling in humid ones and free cooling in cold ones. Modern closed-loop water cooling is said to use annual water equal to a few dozen households. The Energy Efficiency Directive requires heat reuse for new centres above 1 MW, and the largest centres (over 10,000 m²) have a 2030 PUE target of 1.20.
The guide also covers allocation of publicly owned land: a call for expressions of interest or for projects, objective and non-discriminatory criteria, and lease or building-lease contracts. Evaluation criteria include forecast PUE, WUE and energy reuse factor (ERF). It is guidance for public and private parties, not a legal text.
Key points
- About 50 direct operating jobs per 100 MW; local authorities receive TFPB, CFE and CVAE tax revenue.
- Typical large-project need is 50-250 MW with the largest above 1 GW; connections above 40 MW are HTB (high voltage), below it HTA.
- Grid connection takes 2-3 to 6-9 years; accelerated 3-4 year connection is foreseen for identified sites above 400 MW.
- Under the zero net land take (ZAN) rule, data centres do not count against national quotas but against local or regional ones; industrial zones and brownfield sites are favoured.
- Cooling suggestions: dry air in water-stressed areas, indirect closed-loop evaporative in humid areas, free cooling in cold areas, direct liquid cooling in hot areas.
- The Energy Efficiency Directive (2023/1791) requires new data centres above 1 MW to reuse waste heat unless technically impossible.
- The largest centres (over 10,000 m²) have a 2030 PUE target of 1.20 (tertiary decree).
- Data centres above 10 MW are treated as industrial projects; public land is allocated through calls for interest, objective criteria and leases.
- New closed-loop water-cooled sites use annual water comparable to a few dozen households.
Using it in design
- In early site screening check the grid point and HTB proximity first, then land status (brownfield, ZAN) and water stress.
- Plan the schedule with a 2-3 to 6-9 year connection range; electrical connection is the critical path.
- Select the cooling concept by territory type and keep dry cooling as the default alternative on water-stressed sites.
- Include the waste-heat outlet and heat-network connection point in the first layout, and state PUE, WUE and ERF forecasts in the application.
Who should read it
Developers, local authorities, landowners and consultants siting data centres in France.
Document contents
- What is a data centre
- Why install data centres in France
- Which sites are suitable
- Allocating a strategic site
- Project owner, landowner or authority: how to get support
Publication details
- Authors
- Direction générale des Entreprises
- Publisher
- Direction générale des Entreprises
- Year
- 2025
- Document language
- French
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official public publisher source inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only. Local downloads are research evidence, not a redistribution package.
Citation
Direction générale des Entreprises (2025). Guide d’accompagnement: Implantation de centres de données. Direction générale des Entreprises. https://www.entreprises.gouv.fr/files/files/Publications/2025/Guide/25112025__Guide%20Datacenters.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.