Data Centre Standard (ICTA.2.2.002:2023)
Original title Data Centre Standard
ICT Authority Kenya
Kenya ICT Authority's third-edition government data centre standard (effective 1 July 2023) requires at least Tier 2 for public data, 1.2 m cold and 1.0 m hot aisles, and UPS batteries sized for at least 8 hours.
On this page
Overview
ICTA.2.2.002:2023 is the third edition of the Kenya ICT Authority's standard for government data centres (MCDAs); approved 3 May 2023, effective 1 July 2023, with review after three years. It covers site selection, design, layout, cabling, environment, physical security, information security, infrastructure, operations, and maintenance and service-level agreements.
The site and design section requires Ministry of ICT approval of projects, at least Tier 2 for data centres holding public data, a feasibility study and a site selection checklist. Protection against floods, lightning, earthquake and fire is expected; the building must not be in an airport flight path, at least 0.8 km from a railroad or major highway, and at least 0.4 km from an airport, research lab, chemical plant, landfill, river, coastline or dam.
Technical requirements are specific: cold aisle at least 1.2 m and hot aisle at least 1.0 m; front clearance at least 1 m (1.2 m preferred) and rear clearance at least 0.6 m (1 m preferred); 24/7/365 HVAC on backup generator; generator and UPS mandatory with batteries supporting the centre for at least 8 hours; fire separation of at least 1 hour, NFPA-75 compliance and pre-action sprinklers in computer rooms; backbone cabling of at least 24-core 50 micron fibre.
It is a compliance standard rather than a design guide; many numeric design parameters (cooling capacity, efficiency) are left to manufacturers and the Tier level. Appendix I defines Tier 1-4 redundancy and Appendix II gives the site selection checklist. Suppliers must provide a service level agreement with at least 99.99% availability.
Key points
- Every data centre holding public data must be at least Tier 2; every centre must fall within the Tier 1-4 classification.
- Cold aisle at least 1.2 m, hot aisle at least 1.0 m; front clearance at least 1 m (1.2 m preferred), rear at least 0.6 m (1 m preferred).
- Every data centre has generator and UPS; batteries must support the centre for at least 8 hours; distribution through PDUs.
- A dedicated 24/7/365 HVAC system with automatic dampers on backup generator is required; cabinets form hot and cold aisles; blanking panels in unused spaces and perforated floor tiles in cold aisles.
- Site distances: at least 0.8 km from a railroad or major highway; at least 0.4 km from an airport, research lab, chemical plant, landfill, river, coastline or dam.
- Fire: separated from other occupancies by at least 1-hour fire-rated construction; NFPA-75; pre-action sprinklers and water drainage in the computer room.
- Cabling: laser-optimised 50 micron fibre backbone of at least 24 cores; power and communication on separate pathways or a physical barrier; 300 mm minimum access headroom between trays.
- Floor and heights: raised floor minimum 18 inches; racks preferably no taller than 2.1 m with 2.4 m as the cabinet upper limit.
- Supplier SLAs guarantee at least 99.99% data-centre service availability; a single entry point, intruder detection and CCTV are required.
Using it in design
- Target at least Tier 2 redundancy for public data and show N+1 component redundancy on the power and cooling single-line drawings.
- Verify 1.2 m cold aisle, 1.0 m hot aisle and front/rear service clearances on the layout plan.
- Size UPS battery autonomy to the 8-hour requirement; include generator-backed HVAC and sprinkler drainage in the design.
- Add flight path, the 0.8 km and 0.4 km distances, and flood, lightning and earthquake risk to the site checklist.
- Plan separate pathways for power and data; specify the 24-core 50 micron fibre backbone and a labelling scheme.
Who should read it
Engineers and contractors designing or auditing Kenyan government data centres, and policy teams preparing a similar national standard.
Document contents
- Introduction
- Scope
- Application
- Normative references
- Definitions
- Abbreviations
- Data center site selection, design and planning
- Planning layout: cooling, power, fire detection and suppression
- Cabling infrastructure
- Environment
- Physical security
- Information security
- Data center infrastructure
- Data center operations
- Maintenance and SLAs
- Appendix I: Tiered reliability standard
- Appendix II: Site selection checklist
Publication details
- Authors
- ICT Authority Kenya
- Publisher
- ICT Authority Kenya
- Year
- 2023
- Document number
- ICTA.2.2.002:2023
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Public official source inspected; no document-specific commercial redistribution permission established. Original short summaries and metadata only; downloads are local research evidence. PDF p. 2 expressly reserves ICTA copyright and reproduction rights.
Citation
ICT Authority Kenya (2023). Data Centre Standard. ICT Authority Kenya. ICTA.2.2.002:2023. https://cms.icta.go.ke/sites/default/files/2023-07/Data%20Center%20Standard-Third%20Edition%202023.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.