Technical guideFree to read2026

OCP Ready v2 for Hyperscale Data Center Site Assessment, v1.0 rev1.15 (example assessment: Aligned Data Centers PHX04)

Open Compute Project Foundation · Aligned Data Centers (self-assessment), Open Compute Project OCP Ready programme

A completed OCP Ready v2 hyperscale self-assessment for Aligned PHX04 (Chandler, USA): 50.7 MW critical IT, Tier 3-class power and cooling, and design PUE below 1.3 at 80% utilisation.

On this page

Overview

The document is version 1.0 rev1.15 of the Open Compute Project Foundation's OCP Ready v2 site assessment template for hyperscale tenants, illustrated with the self-assessment of Aligned Data Centers' PHX04 facility in Chandler, Arizona. The site is a fully leased wholesale data centre; status is meets requirements, with the original assessment on 29 August 2024 and re-assessment on 26 August 2026.

The v2 template is broader than v1: campus access and logistics (truck circulation, perimeter security), IT technical space (structure, electrical, cooling), meet-me rooms and outside-plant fibre, operations and spares, efficiency, openness and certifications. On security it expects more than 3 access layers, a 24/7 staffed checkpoint and a perimeter fence of at least 2.43 m.

Values reported for PHX04: 160,500 sq ft of white space, 50.7 MW of critical IT power, a block-redundant 6+1 generator and UPS system with static transfer switches, N+N feeds to PDUs, and 12+2 chiller redundancy with thermal energy storage and dual-powered cooling arrays. Power and cooling are rated class 3 (BICSI F3 or Uptime Tier 3 equivalent) with Uptime certification in process.

On efficiency the design PUE at full load is below 1.3 at 80% maximum utilisation; the site has operated for under a year, so annualised PUE is not yet reported. The cooling design needs no water, so WUE monitoring is not applicable. The document is a checklist rather than a standard, showing the evidence behind each requirement.

Key points

  1. Delivery path: storage and IT space access at least 2.75 m high x 1.6 m wide; floor loads 680 kg rolling and 1,221 kg/m² uniform on slab on grade; IT space clear height at least 4.5 m.
  2. Freight lift at least 3,000 kg and 2.75 m door height; a 1.5 m cabin depth is rated Acceptable.
  3. Security: perimeter fence of at least 2.43 m with intrusion detection, backed-up lighting, 24/7 checkpoint, more than 3 access levels, video archive over 30 days (90 days targeted).
  4. Electrical: 2N (A+B) feeds to the row, 47-63 Hz, overhead busbar, N+N UPS feed; generator load acceptance under 35 seconds rated Acceptable.
  5. Cooling: 12+2 chiller redundancy, thermal energy storage, front-to-back airflow, maximum rack density at least 12 kW, MERV 8 filters on outside air.
  6. Network: 3 diverse outside-plant entrances, N+N isolated meet-me rooms, each with two diverse pathways and conduits of at least 100 mm.
  7. Efficiency: design PUE below 1.3 at 80% utilisation; PUE and WUE tracked monthly with billing calculations, live monitoring being developed.
  8. Certifications: 3 Green Globes achieved, Uptime certification in process; operations aligned with the OCP Critical Facility Operations Guidelines.

Using it in design

  • Carry the delivery path, lift and floor-load table into the project brief for hyperscale tenants.
  • Show power and cooling redundancy (for example 6+1 blocks and 12+2 chillers) against the class 3 requirement and prove generator load acceptance time.
  • Verify three diverse entrances, N+N isolated meet-me rooms and dual pathways on the layout plan.
  • State the utilisation point (here 80%) and the method behind any declared PUE.

Who should read it

Wholesale data-centre designers and tenant engineers working with hyperscale customers.

Document contents

  1. Campus site access and logistics
  2. Access controls and monitoring
  3. Ramps and freight lifts
  4. IT technical space: structural, electrical, cooling
  5. Access providers and outside plant fibre
  6. Meet-me rooms
  7. Operations and spare parts
  8. Efficiency
  9. Openness
  10. Certifications

Related standards

  • OCP Ready programme
  • BICSI 002
  • OCP Colocation Facility Guidelines

Publication details

Authors
Aligned Data Centers (self-assessment); Open Compute Project OCP Ready programme
Publisher
Open Compute Project Foundation
Year
2026
Document number
v1.0 rev1.15
Document language
English
Source type
Industry body
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Published OCP Ready site assessment; no licence statement in the document.

Citation

Aligned Data Centers (self-assessment); Open Compute Project OCP Ready programme (2026). OCP Ready v2 for Hyperscale Data Center Site Assessment, v1.0 rev1.15 (example assessment: Aligned Data Centers PHX04). Open Compute Project Foundation. v1.0 rev1.15. https://www.opencompute.org/wp-content/uploads/2026/10/OCP-Ready-v2-for-Hyperscale-Data-Center-Site-Assessment-v1.0-rev1.15-Aligned-Data-Centers-PHX04.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.