AEG Power Solutions

AEG Power Solutions ProtectPlus S500, a 250-600 kVA transformer-less three-level IGBT UPS: 95.2-95.7% double-conversion efficiency, up to 99% in ECO mode, input THDi below 3% and up to 8 units in parallel.

On this page

Overview

The document is a two-page brochure for the ProtectPlus S500 family. The product is a monolithic transformer-less three-level IGBT UPS rated 250, 300, 400, 500 and 600 kVA (kW), classed VFI SS 111. AC/AC efficiency in double conversion is 95.2 to 95.7%; in ECO mode it can exceed 99% and in Smart ECO mode 98% at nominal load. Input power factor is above 0.99 and input THDi is below 3% with a full linear load.

Output power factor reaches 1 (0-35 °C) and the load range from 0.5 inductive to 0.5 capacitive needs no derating. Output THDv is below 1% on a linear load. The inverter carries 125% for 10 minutes and 150% for 60 seconds; the bypass line carries 125% continuously. The battery line is nominally 480 Vdc with 40 blocks of 12 V by default; 38 to 44 blocks are settable, 32 to 44 with derating to PF 0.8. VRLA and Li-ion are supported and charge current is 25-100 A.

Dimensions are 1000 x 900 x 1950 mm and 750 kg for 250-400 kVA and 1400 x 900 x 1950 mm and 1100 kg for 500-600 kVA. Operating temperature is 0-40 °C (up to 50 °C with derating), no altitude derating below 1500 m, noise below 75 dB at 1 m. Standards are IEC EN 62040-1, -2 and -3. The maker states the data carry no binding warranty, and ECO and some values are conditional.

Key points

  1. 250, 300, 400, 500, 600 kVA; kW = kVA (output PF up to 1); VFI SS 111.
  2. AC/AC efficiency 95.2-95.7% in double conversion; >99% in ECO mode, >98% in Smart ECO mode (nominal load).
  3. Input PF >0.99, input THDi <3%; input voltage 380/400/415 V.
  4. Overload: inverter 125% for 10 min, 150% for 60 s; bypass 125% continuous, 150% for 10 min.
  5. Nominal battery voltage 480 Vdc, 40 blocks of 12 V (38-44 settable), charge current 25-100 A.
  6. Up to 8 units in parallel; static and maintenance bypass standard.
  7. 250-400 kVA: 1000 x 900 x 1950 mm, 750 kg; 500-600 kVA: 1400 x 900 x 1950 mm, 1100 kg.
  8. Operation 0-40 °C (to 50 °C with derating), no derating below 1500 m, noise <75 dB.

Using it in design

  • In a data-hall UPS room, weigh the ECO and Smart ECO efficiency gain against the lower protection class in those modes.
  • Use input THDi <3% and PF >0.99 to reduce generator oversizing and the need for input filters.
  • Select battery block count (38-44) together with DC bus voltage and PF derating.
  • Use the 750 and 1100 kg weights for floor loading and the 1000 or 1400 mm width for layout.
  • Plan paralleled systems against the 8-unit limit.

Who should read it

Electrical engineers selecting UPS units for medium and large data centres and critical facilities.

Document contents

  1. Features and benefits
  2. Typical applications
  3. Specifications: mains input, bypass, output, battery, user interface
  4. General and standards

Publication details

Authors
AEG Power Solutions
Publisher
AEG Power Solutions
Year
Year not stated
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

No document-specific redistribution permission was established. Bibliographic reference only.

Citation

AEG Power Solutions AEG Protect Plus S500 English datasheet 04/2021 V1, p.2. AEG Power Solutions. https://www.upss.ro/web/b2b/images/uploaded/products/PDF/AEG_PROTECT_PLUS_S500_EN_1.PDF

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.