Singapore IMDA request for information (20 March 2026): servers and storage that are ENERGY STAR certified and meet at least ASHRAE Class A2 can be pre-approved for the Energy Efficiency Grant; submissions close 10 April 2026.

On this page

Overview

The document, prepared by the Digital Infrastructure Division of Singapore's Infocomm Media Development Authority (IMDA), is a request for information on the Energy Efficiency Grant (EEG) for the data centre sector, launched in December 2024. The grant supports data-centre end users in moving to energy-efficient IT equipment, and the pre-approved equipment list is published on the GoBusiness website. The document is about five pages, mostly legal disclaimers and submission procedure, with no technical data.

IMDA invites vendors to submit information on servers and storage devices to be considered for the pre-approved list. There are two pre-approval criteria: the equipment must be certified by ENERGY STAR against its Program Requirements for Computer Servers and Storage Devices for Data Centres, and it must minimally comply with Class A2 of the ASHRAE Environmental Classes for Data Centres. Only models meeting these criteria are evaluated, and the final list decision rests with IMDA.

The process is information gathering and not a procurement. Information must be submitted in English, clearly and concisely, using the template provided; only complete submissions are considered and proprietary or commercially sensitive information must be clearly marked. The closing date is 10 April 2026 at 17:00. IMDA may end the RFI or change its scope at any time.

Key points

  1. Issued 20 March 2026; submissions close 10 April 2026 at 17:00.
  2. The Energy Efficiency Grant (EEG) was launched in December 2024 to support data-centre end users in adopting energy-efficient IT equipment.
  3. Pre-approval criterion 1: ENERGY STAR certification to the Program Requirements for Computer Servers and Storage Devices for Data Centres.
  4. Pre-approval criterion 2: compliance with at least Class A2 of the ASHRAE Environmental Classes for Data Centres.
  5. The pre-approved list is published publicly on the GoBusiness website; the list decision rests with IMDA.
  6. The document is not a procurement and creates no binding obligation on IMDA.
  7. Only complete submissions are evaluated; sensitive information must be clearly marked.

Using it in design

  • For Singapore projects, pre-screen server and storage selection for grant eligibility with ENERGY STAR certification and ASHRAE A2 compliance.
  • Match the A2 class operating envelope of the IT equipment to the temperature and humidity limits of the cooling design.
  • Add the ENERGY STAR certificate number and environmental class fields to the equipment standards list.
  • Confirm that models used in a grant application appear on the GoBusiness pre-approved list.

Who should read it

Operators selecting data-centre IT equipment in Singapore, server and storage vendors, and teams preparing grant applications.

Document contents

  1. Disclaimer
  2. Introduction
  3. Pre-approval criteria for energy-efficient IT equipment
  4. Submission of information
  5. Confidentiality of information
  6. Closing date and enquiries

Publication details

Authors
Infocomm Media Development Authority (IMDA)
Publisher
Infocomm Media Development Authority (IMDA)
Year
2026
Document number
IMDA EEG RFI, issued 20 March 2026
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official PDF text opened through TinyFish; normal curl download also attempted. Metadata and original short summary only. No ASHRAE document content was extracted.

Citation

Infocomm Media Development Authority (IMDA) (2026). Request for Information: Energy-Efficient Data Centre IT Equipment. Infocomm Media Development Authority (IMDA). IMDA EEG RFI, issued 20 March 2026. https://imda.gov.sg/-/media/imda/files/industry-development/call-for-proposals/request-for-information-rfi-energy-efficient-data-centre-it-equipment/2026/eeg-rfi-final.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.