Kuru Tip Transformatörler İçin İşletim ve Bakım Kılavuzu (Operation and Maintenance Manual for Dry-Type Transformers)

Original title Kuru Tip Transformatörler İçin İşletim ve Bakım Kılavuzu

Sönmez Trafo

Sönmez Trafo's manual KY.KD-16, dated 3 April 2014 (revision 2), covers receipt, installation, commissioning and maintenance of cast-resin dry-type transformers; for ventilation it requires 3 m³ of air per minute for each kilowatt of total losses, and for parallel operation an impedance difference of no more than 10%.

On this page

Overview

The 12-page Turkish-language manual gathers the manufacturer's rules for safe transport, installation, operation and maintenance of its dry-type transformers. It cites IEC 60076-11 for dry-type transformers and ANSI C57.94 and IEC 60905 as operation and maintenance guides. There are seven sections: introduction and safety, receipt, installation, commissioning, maintenance, taking out of service and possible problems in service. From the outset it requires that all work is done by competent personnel and that the supply is isolated and the main switch locked before maintenance.

The receipt section sets transport limits: only vehicles with pneumatic suspension are used on the road, acceleration must not exceed 1 g in the direction of travel or 0.5 g in turns, and the transformer travels upright. The risk of tipping is stressed because the centre of gravity is high. The installation section treats siting in terms of personnel safety, access, ventilation, atmospheric conditions and noise level. The location must be free of dripping water, heavy humidity, condensation and metallic dust; where these cannot be avoided, an enclosure of suitable IP rating or anti-condensation heaters must be requested in the order.

Two numeric rules are given for ventilation: 3 m³ of air per minute for each kilowatt of total losses, and in naturally cooled rooms 0.1 m² of inlet and of outlet opening for every 100 kVA. The transformer is kept at least 30 to 45 cm from the wall. Recommended clearances for bare conductors are 115 mm at Um 12 kV, 215 mm at 24 kV and 300 mm at 36 kV. Minimum torque values are tabulated for M8 to M16 bolts on busbar and tap connections. Connection cables must be supported and fixed against electrodynamic forces during a short circuit.

The commissioning section covers parallel operation, loading, temperature control and tap changing. Transformers that run in parallel must have the same voltages, ratios and vector group indices, and their impedances must not differ by more than 10%. On overload the manual gives no general guidance: because the thermal capacity and time constants of dry-type transformers vary with construction, it directs users to the manufacturer. Temperature protection works with alarm and trip stages set 20 °C apart. Maintenance consists of a fan and temperature-control check every six months and dust cleaning. The final section matches fault symptoms to their likely causes.

Key points

  1. Required air volume: 3 m³ per minute for each kilowatt of the transformer's total losses.
  2. Naturally cooled rooms need 0.1 m² of inlet and 0.1 m² of outlet opening per 100 kVA; the transformer is not placed closer than 30 to 45 cm to the wall.
  3. Bare-conductor clearances (for the 1000 m altitude condition): 115 mm for Um 12 kV, 215 mm for 24 kV, 300 mm for 36 kV.
  4. In parallel operation the voltages, ratios and vector group indices must match, and the impedance difference must never exceed 10%.
  5. Maximum temperatures: 155 °C for class F transformers and 180 °C for class H; the trip relay is never set above these values.
  6. Temperature monitoring uses sensors in the low-voltage windings in two stages with a nominal setting difference of 20 °C: the lower stage alarms and the higher stage trips.
  7. Listed causes of overheating include overload, ambient temperature above 40 °C (or the value stated in the order) and inadequate cooling.
  8. Minimum torque values (busbar connections): M8 20 Nm, M10 40 Nm, M12 70 Nm, M14 90 Nm, M16 130 Nm.
  9. Transport: pneumatic-suspension vehicle, at most 1 g in the direction of travel and 0.5 g in turns, upright position.
  10. Maintenance: fans and temperature control are tested every 6 months; a dust check follows at least 6 months after installation, with cleaning by vacuum, dry compressed air and cloths.

Using it in design

  • Calculate transformer room ventilation with the rule of 3 m³ per minute per kW of losses; for natural ventilation, check 0.1 m² of inlet and outlet opening per 100 kVA as the minimum.
  • In the layout, leave at least 30 to 45 cm between transformer and wall, and confirm the 115, 215 or 300 mm bare-conductor clearance for the Um on the medium-voltage side.
  • Specify transformers that will run in parallel with the same voltage, ratio and vector group and an impedance difference of at most 10%.
  • Do not assume a general overload allowance for a dry-type transformer in the design; if temporary overload is needed, obtain a value for that unit from the manufacturer.
  • Wire the alarm and trip contacts of the temperature relay to the monitoring system and the circuit breaker, and check the settings against the insulation class (155 °C for F, 180 °C for H).
  • For humid or dusty locations, state the enclosure IP rating and anti-condensation heaters in the order; for harmonic-producing loads such as UPSs, review the overheating risk with the manufacturer.

Who should read it

Electrical engineers designing dry-type transformer rooms, commissioning teams and operations staff maintaining transformers.

Document contents

  1. 1.0 Giriş (Introduction): general, precautions, health and safety
  2. 2.0 Teslim Alma (Receipt): shipping arrangements, recommended checks, unloading and handling, storage
  3. 3.0 Kurulum (Installation): location and site preparation, final checks before energising, electrical connections and earthing, torque values
  4. 4.0 Devreye Alma (Commissioning): placing in service, parallel operation, loading, temperature control, tap changing
  5. 5.0 Bakım Onarım (Maintenance)
  6. 6.0 Devreden Çıkartma (Taking out of service)
  7. 7.0 Devredeyken Olası Sorunlar (Possible problems in service): electrical circuits, magnetic circuits, insulating parts, remedies

Publication details

Authors
Sönmez Trafo
Publisher
Sönmez Trafo
Year
2014
Document number
KY.KD-16, rev. 2, 03.04.2014
Document language
Turkish
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official publisher material inspected. No document-specific commercial redistribution permission established; retain metadata and original short summaries only.

Citation

Sönmez Trafo (2014). Kuru Tip Transformatörler İçin İşletim ve Bakım Kılavuzu. Sönmez Trafo. KY.KD-16, rev. 2, 03.04.2014. https://sonmeztrafo.com.tr/Doc/Dokumanlar/KY.KD-16%20Kuru%20tip%20%20Kullanma%20K%C4%B1lavuzu%20-%20T%C3%BCrk%C3%A7e-Rev2%20%20%20%20%28%C4%B0ngilizce%20Rev-3%20ile%20ayn%C4%B1%29.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.