The Data Centre Covenant, UK Government
Original title The Data Centre Covenant
UK Government
The UK government's Data Centre Covenant: a target of 6 GW of AI data centre capacity by 2030, PUE of 1.3 or better for new facilities, and priority grid connection for strategic data centres.
On this page
Overview
The document is the UK government's Data Centre Covenant for AI data centres (Open Government Licence v3.0). The government estimates that 6 GW of AI data centre capacity will be needed by 2030 to protect the national interest, and argues that the NHS, defence and other critical services should not depend almost entirely on infrastructure overseas. The Covenant sets new tests that all data centres are encouraged to meet and that strategic data centres must meet to qualify for additional government support.
Five tests are listed: lower electricity bills (data centres pay for the energy costs they create, make credible commitments for the grid capacity they request and support grid flexibility); invest in local communities (strategic data centres agree a Local Benefit Plan tied to size); the highest environmental standards; jobs, apprenticeships and reindustrialisation; and strengthening Britain's security (working with the NCSC, cyber resilience, planning with critical suppliers).
Under the environmental test, new facilities are expected to be designed for a Power Usage Effectiveness (PUE) of 1.3 or better, minimise public water demand with technologies such as closed loop water systems, publish annual energy and water consumption reports, and capture waste heat for nearby homes, schools, hospitals or businesses where a viable local user exists. Strategic data centres report annually on energy, water, efficiency, emissions, heat reuse and participation in flexibility services.
In return the government will set up a Ministerial Control Centre chaired by the Minister for AI. For strategic sites it plans to reserve and reallocate connections, identify additional capacity before 2030, facilitate transfer of pre-2030 connection contracts and develop a tightly controlled framework allowing on-site generation until a grid connection is secured for exceptional projects. The definition of a strategic data centre will be set out later.
Key points
- The government estimates that 6 GW of AI data centre capacity will be needed by 2030.
- Five tests: low electricity bills, investment in local communities, high environmental standards, jobs and reindustrialisation, security.
- New facilities should aim for PUE 1.3 or better and use technologies such as closed loop water systems to reduce public water demand.
- Strategic data centres publish annual reports on energy and water use, efficiency, emissions, heat reuse and flexibility participation.
- Waste heat should be captured for nearby homes, schools, hospitals or businesses where a viable local user exists.
- Strategic data centres agree a Local Benefit Plan with investment linked to size.
- The government will reserve and reallocate connections, seek additional pre-2030 capacity and develop a tightly controlled framework for temporary on-site generation in exceptional projects.
- The draft Data Centre National Policy Statement will go to consultation; five AI Growth Zones continue to be delivered.
Using it in design
- Set a design target of PUE 1.3 or better for new facilities and show by calculation that the cooling and power distribution architecture meets it at part load too.
- To cut water use favour closed loop cooling and include metering (sub-meters) for annual total and peak water and power in the design.
- For waste heat recovery identify the nearby heat user (homes, schools, hospitals, businesses) at feasibility stage and plan the heat output temperature accordingly.
- Document grid capacity requests realistically; build load flexibility (backup generation, storage) into the architecture for participation in flexibility services.
- Design cyber and physical resilience to critical infrastructure expectations (NCSC cooperation, supplier disruption planning).
Who should read it
Investors, designers, and grid and planning consultants developing AI data centres in the UK.
Document contents
- Introduction and National Interest
- 1. Lower Electricity Bills
- 2. Invest in Improving Local Communities
- 3. Adhere to the Highest Environmental Standards
- 4. Create Jobs, Apprenticeships and Drive Reindustrialisation
- 5. Strengthen Britain's Security
- Government Support: Ministerial Control Centre and Grid Connections
- Wider Reforms
Publication details
- Authors
- UK Government
- Publisher
- UK Government
- Year
- 2026
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official public publisher source inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only. Local downloads are research evidence, not a redistribution package.
Citation
UK Government (2026). The Data Centre Covenant. UK Government. https://www.gov.uk/government/publications/data-centre-covenant/the-data-centre-covenant