Overview
The document is the summary meeting notes of a roundtable held by the UK Government Office for Science on 20 February 2026, chaired by Government Chief Scientific Adviser Professor Dame Angela McLean. The question is where the UK should locate domestic data centres to meet future AI and non-AI demand. The notes are not a statement of government policy; they reflect the combined views of participants from academia, industry and government on the day, and are published under the Open Government Licence v3.0.
The demand section says there is no obvious framework to determine how much onshore capacity the UK will need. Demand will be variable and geographically dynamic, and will depend on the pace of AI adoption, sovereign data policy and the regulatory environment. Given the uncertainty, over-provisioning may be needed for resilience. Cloud data centres are merging general and AI facilities, and siting should be thought of by type of task rather than sector.
The use cases, latency and security section points to the difference in power density and cooling per rack between edge computing and AI-focused hyperscale centres. Training workloads are generally less latency sensitive; for some large language models demand has shifted from training to inference. Financial services need very low latency, image processing (agriculture, transport) needs local centres, and public services and regulated industries generally need onshore centres.
Other siting issues: there is no national planning guidance; an interactive map of all data centres, fibre routes and power lines is proposed; and public acceptance depends on the credibility of local benefits and on transparency. Grid connection delays are a main siting factor. Water is not a major constraint in the UK, since waterless cooling is possible with closed loops or ventilation, though less water means more power. Waste heat reuse depends on proximity to district heat networks.
Key points
- There is no obvious framework to determine how much onshore data centre capacity the UK will need; demand is very hard to estimate.
- Critical siting factors are latency, data sensitivity, carbon emissions and reliable provision of services.
- Training workloads are generally less latency sensitive; inference has become prominent for some large language models.
- There is currently no national planning guidance for data centre siting; international examples such as the Netherlands and Saudi Arabia can be consulted.
- Grid connection delays are a key factor in siting decisions.
- Water is not a major constraint; AWS data centres reportedly use no water for around 97% of the year, but using less water means using more power.
- For carbon, co-location with renewable or low carbon-intensity generation should be incentivised.
- Waste heat reuse depends on district heat networks; laundry services, food preparation and greenhouses are named as possible uses.
Using it in design
- In site selection treat grid connection delay as the main risk and put the connection date on the project critical path.
- For latency-sensitive workloads prioritise fibre route quality and proximity; for training workloads prioritise cost and power access.
- In cooling design compare waterless or low-water options and the water-power trade-off; reflect regional flood risk in cooling plant placement.
- State site resilience scenarios for climate change (flooding patterns, temperature, water availability) in the design basis.
- Include waste heat recovery in scope only if heat-receiving infrastructure exists nearby; otherwise leave it out of the first phase.
Who should read it
Developers, designers and public decision makers assessing data centre siting, planning and policy in the UK.
Document contents
- Summary of Meeting Notes
- Estimating Future Demand
- Use Cases, Latency and Security
- Wider Considerations on Location
- Power, Water, Carbon, Climate and Waste Heat
- Meeting Participants
Publication details
- Authors
- UK Government Office for Science
- Publisher
- UK Government Office for Science
- Year
- 2026
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Publication-specific opening notice explicitly licenses the publication under OGL v3.0, except otherwise stated and third-party copyright. Attribution and third-party conditions remain applicable.
Citation
UK Government Office for Science (2026). Data centre siting in the UK. UK Government Office for Science. https://www.gov.uk/government/publications/data-centre-siting-in-the-uk/data-centre-siting-in-the-uk
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.