Technical guideFree to read2025

Options for optimising GB Data Centres

National Energy System Operator (NESO)

NESO's NIA2_NESO098 project (close-down report July 2025) examines location, connection availability, telecoms, labour and water constraints for British data centres, flagging inconsistent capacity definitions and speculative applications as forecasting risks.

On this page

Overview

The project is the National Energy System Operator's (NESO) completed grid-planning research (project record NIA2_NESO098). It considers location, connection availability, telecoms, labour and water constraints for Great Britain's data centres.

The lessons highlight inconsistent capacity definitions and speculative queue entries as forecasting risks. In particular, quoted IT power is distinguished from total demand including cooling, and attention is drawn to duplicate speculative connection applications.

Key points

  1. Project record NIA2_NESO098; the close-down report is listed as July 2025.
  2. The research covers location, connection availability, telecoms, labour and water constraints.
  3. Quoted IT power should be distinguished from total demand including cooling.
  4. Speculative duplicate connection applications create demand forecasting risk.
  5. Inconsistent capacity definitions are a forecasting risk.

Using it in design

  • In a connection application state clearly whether the MW figure is IT power or total demand including cooling.
  • Remove duplicate applications from demand forecasts so capacity planning rests on realistic queue data.
  • In site selection score telecoms, labour and water constraints together with connection availability.
  • Plan phased growth while documenting the definition behind the declared capacity.

Who should read it

Developers, grid planners and policy analysts working on data-centre connection and siting in Great Britain.

Publication details

Authors
National Energy System Operator (NESO)
Publisher
National Energy System Operator (NESO)
Year
2025
Document number
NIA2_NESO098
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official public publisher text inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only.

Citation

National Energy System Operator (NESO) (2025). Options for optimising GB Data Centres. National Energy System Operator (NESO). NIA2_NESO098. https://www.neso.energy/about/innovation/our-innovation-projects/options-optimising-gb-data-centres

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.