All-Island Resource Adequacy Assessment 2026-2035

EirGrid and SONI · EirGrid, SONI

EirGrid and SONI 10-year report: Ireland is outside its 3-hour LOLE reliability standard in 2026-2028, and data centre and new technology load rises from 959 MVA in 2024 to 1,870 MVA by 2035 in the median scenario.

On this page

Overview

The transmission system operators EirGrid (Ireland) and SONI (Northern Ireland) publish a resource adequacy assessment that examines the balance of demand and supply on the island's electricity system over the next 10 years. It continues the former Generation Capacity Statement under an updated methodology aligned with the European Clean Energy Package. This year's report also includes a new Economic Viability Assessment required by Article 24 of EU Regulation 2019/943. The data freeze date is 30 June 2025.

Adequacy is measured against the reliability standard set by the department and the regulator; for Ireland it is 3 hours LOLE (expected hours a year when supply is not expected to meet demand). In the median demand scenario both the base and secure assessments are outside the standard in 2026-2028, with the Celtic interconnector improving the position from 2028. After 2029 the base assessment shows a surplus, while the secure assessment shows a deficit of about 200 MW rising to over 400 MW in 2034.

Data centres and new technology loads (NTLs) are a significant demand driver. About 2,100 MVA is contracted at transmission level and about 300 MVA at 110 kV distribution level, almost all in the greater Dublin region. The forecast covers 17 transmission-level and 5 distribution-level data centre projects that are connected or have a signed connection agreement, and assumes data centres have a flat daily profile that ramps gradually towards contracted load.

The report also covers Temporary Emergency Generation (TEG) and Retain Existing Units (REU) programmes, the Dublin short-circuit constraint, annual run-hour limitations (ARHL) and about 3,200 MW of conventional capacity over 30 years old by 2035. Part A is a plain English summary for Ireland; the remainder is detailed analysis.

Key points

  1. Ireland's reliability standard is 3 hours LOLE; in the median scenario both base and secure assessments are outside it throughout 2026-2028.
  2. After 2029 the base assessment shows a surplus; the secure assessment starts at a deficit of about 200 MW and exceeds 400 MW in 2034.
  3. About 2,100 MVA at transmission level and about 300 MVA at 110 kV distribution are contracted to data centres and new technology loads, almost all in greater Dublin.
  4. The forecast covers 17 transmission-level and 5 distribution-level data centre projects.
  5. Data centre and NTL demand is 959 MVA in 2024; in 2035 it is 1,402 MVA (low), 1,870 MVA (median) and 2,183 MVA (high), growth of 443, 911 and 1,225 MVA.
  6. Under CRU/21/124, new data centres are assessed on criteria including ability to bring on-site dispatchable generation or storage equal to or above peak demand; only one new data centre met this by the freeze date.
  7. CRU's new Large Energy Users Connection Policy was published on 16 December 2025; EirGrid and ESB Networks must publish an application process by 31 March 2026.
  8. The secure assessment assumes some new units are limited to 1,500 hours of annual run (ARHL).
  9. About 3,200 MW of conventional capacity will be over 30 years old by 2035.
  10. Few data centre sites offer flexible demand; in emergencies large energy users may be required to cut demand under mandatory demand reduction.

Using it in design

  • When planning a new Irish data centre, treat the CRU Large Energy Users Connection Policy and the expectation of on-site dispatchable generation or storage as inputs to the backup power design.
  • Assess connection timing in greater Dublin together with the 2026-2028 adequacy shortfall and the Dublin short-circuit constraint.
  • A flat profile and gradual ramp for data centre load underpin grid planning; declare your own load ramp plan consistently with that assumption.
  • Design a circuit architecture that can shed non-critical load, and a backup generator start method, for the possibility of mandatory demand reduction.
  • Settle backup generator fuel type (for example HVO) and run-hour limits early in the permitting process.

Who should read it

Investors, electrical designers and grid connection advisers planning data-centre connection and power supply in Ireland and Northern Ireland.

Document contents

  1. Part A: plain English summary for Ireland (introduction, assessment, demand forecast, generation forecast, Dublin short-circuit constraint)
  2. Data centres and new technology loads
  3. Total electricity requirement
  4. Resource adequacy results: base and secure assessments
  5. Sensitivity analysis
  6. Economic Viability Assessment

Publication details

Authors
EirGrid; SONI
Publisher
EirGrid and SONI
Year
2026
Document language
English
Source type
Expert / community
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

TSO publication; no open licence stated.

Citation

EirGrid; SONI (2026). All-Island Resource Adequacy Assessment 2026-2035. EirGrid and SONI. https://cms.eirgrid.ie/sites/default/files/publications/AIRAA-2026-2035_Ireland.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.