Technical guideFree to read2016

Preventing arc flash in mission critical facilities

Consulting-Specifying Engineer · Kenneth Kutsmeda

Kenneth Kutsmeda explains why data centres, with large UPSs, big transformers and closed-transition generator paralleling, tend to have high available fault current and arc-flash exposure. He identifies arcing time as the dominant variable and reviews mitigation options.

On this page

Overview

The article appeared in Consulting-Specifying Engineer in 2016. Kutsmeda explains that data centres, with large UPSs, big transformers and closed-transition generator paralleling, tend to have high available fault current and arc-flash exposure.

The author stresses that arcing time is the variable that dominates arc energy. Per IEEE 1584-2002, incident energy depends on arcing current, working distance and arcing time; energy is linear with duration, so clearing time is the key lever. Disabled or delayed instantaneous trips can push clearing to about 2 seconds in the time-delay region.

Mitigation options include revisiting coordination settings, electronic trip units, zone-selective interlocking (ZSI), differential protection, optical sensing, arc-resistant gear, maintenance-mode switches and remote operation. ZSI is recommended for arc-flash mitigation only on UL 1558 switchgear with full section barriers. NEC 240.87 (2014) also requires arc energy reduction on overcurrent devices rated 1,200 A or higher.

In a 14 MW facility case study, a white-space RPP was reduced from 17 cal/cm2 (Level 3 PPE, 91 in. boundary) to 0.17 cal/cm2 (Level 0) by replacing a fixed thermal-magnetic main with a lower-instantaneous breaker, without losing coordination (selectivity). The design recommendations include a preliminary arc-flash study during design and a bypass source so that portions can be de-energized for maintenance.

Key points

  1. Incident energy depends on arcing current, working distance and arcing time; per IEEE 1584-2002 energy is linear with duration.
  2. Disabled or delayed instantaneous trips can push clearing to about 2 s in the time-delay region.
  3. NEC 240.87 (2014) requires arc energy reduction on overcurrent devices rated 1,200 A or higher.
  4. ZSI is recommended for arc-flash mitigation only on UL 1558 switchgear with full section barriers.
  5. Case study: white-space RPP reduced from 17 cal/cm2 (Level 3 PPE, 91 in. boundary) to 0.17 cal/cm2 (Level 0).
  6. The reduction came from a lower-instantaneous breaker, with coordination retained.
  7. Do a preliminary arc-flash study during design and provide a bypass source for maintenance.

Using it in design

  • Run a preliminary arc-flash estimate at design stage and flag white-space panels above about 1.2 cal/cm2 or above PPE category 2.
  • Require arc-energy reduction (ERMS/ZSI/differential) on breakers of 1,200 A or more.
  • Prefer electrical galleries over white-space placement of high-energy gear.
  • Provide a bypass source so portions can be de-energized for maintenance.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Review your power design in SoSo CAD

Inspect supply paths, equipment loads and UPS failure scenarios in one model.

Request a demo
Single-line diagram in the SoSo CAD power and capacity workspace

Who should read it

Engineers designing data center power distribution and protection, and safety and operations managers.

Related standards

  • NFPA 70E-2015
  • IEEE 1584
  • NFPA 70 Art. 240.87
  • UL 1558

Publication details

Authors
Kenneth Kutsmeda
Publisher
Consulting-Specifying Engineer
Year
2016
Document language
English
Source type
Expert / community
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Kenneth Kutsmeda (2016). Preventing arc flash in mission critical facilities. Consulting-Specifying Engineer. https://www.csemag.com/preventing-arc-flash-in-mission-critical-facilities/

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.