Technical guideFree to read2008

Commissioning on-site electrical systems

Consulting-Specifying Engineer · Kenneth Kutsmeda

Kutsmeda adapts ASHRAE Guideline 0's four-phase commissioning process to on-site electrical systems in critical facilities and argues that commissioning must begin in pre-design.

On this page

Overview

Kutsmeda's article adapts ASHRAE Guideline 0's four-phase commissioning process to on-site electrical systems in critical facilities. His central argument is that commissioning must begin in pre-design so that the design supports testing. The article lays out the equipment scope and three test levels: individual equipment, discrete system and integrated system (black-start).

The discrete system level means, for example, testing PDU, UPS and switchgear together under load and on generator. The integrated level covers site-wide black-start with partial failures. The design phase should provide load-bank connections or isolation breakers for phased construction, and control sequences with timer presets for every mode.

In the construction phase, the article notes that factory tests often miss interfaces with controls, mechanical and life-safety systems, so the commissioning authority (CxA) may add witnessed procedures. In a North Carolina data centre case study, a manufacturer-built simulator and phased testing uncovered defective breakers, failure-mode interaction problems and inrush coordination issues.

The commissioned system later rode through a 25 kV utility switch fault without losing critical load; the owner estimated a recovery cost of $5 million had it dropped. The limits of the article are that it rests on a single 2008 case study and that the cost figure is the owner's own estimate. Related documents named are ASHRAE Guideline 0-2005, NETA ATS, IEEE 450, IEEE 1188, NFPA 70E, NFPA 110 and NFPA 111.

Key points

  1. Three test levels: individual equipment, discrete system (e.g., PDU+UPS+switchgear under load and on generator) and integrated site-wide black-start with partial failures.
  2. The design phase must provide load-bank connections or isolation breakers for phased construction, and control sequences with timer presets for every mode.
  3. Factory tests often miss interfaces with controls, mechanical and life-safety systems; the CxA may add witnessed procedures.
  4. Case study testing found defective breakers, failure-mode interaction problems and inrush coordination issues.
  5. A post-commissioning 25 kV utility switch fault was ridden through without losing critical load.
  6. The owner estimated a $5 million recovery cost had the load dropped.

Using it in design

  • For phased builds, the tool should place load-bank connection points and isolation breakers and output a Cx test list with individual, discrete and integrated levels.
  • Include sequence-of-operations timer presets as fields on transfer and paralleling equipment.
  • Involve the commissioning authority from the earliest design stage.
  • Define witnessed site tests for interfaces that factory tests do not cover.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Bring standards pre-checks into your project

Review model-based TS EN 50600 and Tier pre-checks, missing inputs and items requiring engineering review in SoSo CAD.

Request a demo
Selected rule packs and findings in the SoSo CAD standards panel

Who should read it

Engineers and commissioning authorities who design, commission and test electrical systems for critical facilities.

Related standards

  • ASHRAE Guideline 0-2005
  • NETA ATS
  • IEEE 450
  • IEEE 1188
  • NFPA 70E
  • NFPA 110
  • NFPA 111

Publication details

Authors
Kenneth Kutsmeda
Publisher
Consulting-Specifying Engineer
Year
2008
Document language
English
Source type
Expert / community
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Kenneth Kutsmeda (2008). Commissioning on-site electrical systems. Consulting-Specifying Engineer. https://www.csemag.com/articles/commissioning-on-site-electrical-systems/

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.