What do you need to know about designing HVAC systems in data centers? (roundtable)
Consulting-Specifying Engineer · Bill Kosik, Brian Rener et al.
A roundtable in which four mission-critical HVAC engineers share project experience on hot-climate design, air-side economization, unusual heat sinks and the energy-water nexus.
On this page
Overview
This piece is a roundtable discussion published in Consulting-Specifying Engineer in 2023. The participants are Bill Kosik, Brian Rener, Ameya Soparkar and Robert Sty. Four mission-critical HVAC engineers describe recent project experience.
On hot-climate design, a Middle East project is described, designed for 120 F ambient with 95-105 F condenser water, sand-trap louvres and 45-degree underground bends. Phoenix ambient exceeds 115 F; the advice is to relocate air-cooled chillers and generators and to use CFD to avoid exhaust and radiant heat recirculation. The piece also touches on air-side economization with fan-wall air handling units.
Project examples include the University of Utah: up to 10 MW, outside air plus direct evaporative cooling, Tier III, PUE 1.2-1.3, with backup air-cooled chillers running less than 5% of the year. A Korean 10 MW site supplies 75 F and 40% RH via direct outside air, switches to mechanical cooling on Gobi dust events, and reaches PUE 1.25. Colocation chilled water loops are set at 44/56 F for general use and 50/60 F for higher-temperature loops to extend water-side economization.
Unusual heat sinks include snow storage, canal water and in-rack CO2, and thermosyphon coolers are said to perform like towers below about 50 F outdoor temperature with no water use. The discussion also covers the energy-water nexus in drought-restricted regions. As a limit, these are experiences from specific projects and may not apply unchanged in another climate or at another load; they do, however, illustrate with concrete examples the design risks met in hot and arid climates.
Key points
- Middle East project: 120 F ambient, 95-105 F condenser water, sand-trap louvres, 45-degree underground bends.
- Phoenix ambient exceeds 115 F; relocate air-cooled chillers and generators and use CFD to avoid exhaust and radiant heat recirculation.
- University of Utah: up to 10 MW, outside air plus direct evaporative cooling, Tier III, PUE 1.2-1.3, backup chillers run under 5% of the year.
- Korean 10 MW site: 75 F / 40% RH via direct outside air; switches to mechanical cooling on dust events; PUE 1.25.
- Colocation chilled water loops: 44/56 F general and 50/60 F higher-temperature loops to extend water-side economization.
- Thermosyphon coolers perform like towers below about 50 F outdoor with no water use.
- Unusual heat sinks: snow storage, canal water, in-rack CO2.
Using it in design
- Flag hot-climate risks in site design checks: ambient above 115 F, and recirculation between chillers and generator exhaust; suggest CFD.
- Support multiple chilled-water temperature loops per site.
- Report water use alongside energy so dry and evaporative options can be compared.
- For dusty regions, define a changeover scenario to mechanical cooling in the outside-air system.
Monthly newsletter · free
Keep your reading list current
Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.
SoSo CAD
Check cooling capacity alongside your design
Review zone heat loads, available capacity and the capacity balance after the largest unit is lost in SoSo CAD.
Request a demo
Who should read it
Mechanical designers doing data center HVAC and site selection in hot and arid climates.
Related standards
- ASHRAE Thermal Guidelines for Data Processing Environments
Publication details
- Authors
- Bill Kosik; Brian Rener; Ameya Soparkar; Robert Sty
- Publisher
- Consulting-Specifying Engineer
- Year
- 2023
- Document language
- English
- Source type
- Expert / community
- Access
- Free to read
- Licence
- Copyright retained; citation only — the publisher’s terms apply to the original document
Citation
Bill Kosik; Brian Rener; Ameya Soparkar; Robert Sty (2023). What do you need to know about designing HVAC systems in data centers? (roundtable). Consulting-Specifying Engineer. https://www.csemag.com/what-do-you-need-to-know-about-designing-hvac-systems-in-data-centers/
Events on this subject
Browse the events calendarAll content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.