Hitachi Energy

A Hitachi Energy techno-economic study of an "energy hub" for a hypothetical 150 MW GenAI data centre that must start off-grid and connect to the grid later.

On this page

Overview

The study centres on a hypothetical 150 MW site in Virginia. Over a 20-year life it compares a solar PV + BESS + diesel generator hub against generator-only operation, and a PV + BESS hub against grid-only supply, then a transition case that switches to grid after five years.

The basis: 150 MW peak load ranging 75-150 MW, 450 MW of PV ($820/kW), a 150 MW/300 MWh BESS, 150 MW of diesel generation ($300/kW, $3/gal) and grid power at $0.13/kWh plus $20/kW-month. The 450 MW of PV needs roughly 2,700 acres. AI racks are cited as drawing roughly seven times the power of traditional racks.

The off-grid hub cuts generator energy from about 982 GWh to 584 GWh per year against generator-only, and emissions from about 768 kt to 457 kt CO2e, with LCOE of about $0.152/kWh versus $0.20/kWh. The grid-connected hub has LCOE of about $0.123/kWh versus $0.14/kWh and emissions of about 188 kt versus 285 kt CO2e, 34% lower.

The transition case assumes grid interconnection after five years at $240/kW, giving an LCOE of about $0.164/kWh. The results depend on one hypothetical site and on the cost inputs chosen, so the same numbers should not be expected elsewhere.

Key points

  1. Study basis: 150 MW peak (75-150 MW range), 20 years, 450 MW PV ($820/kW), 150 MW/300 MWh BESS, 150 MW diesel ($300/kW, $3/gal), grid $0.13/kWh + $20/kW-month.
  2. 450 MW of PV needs roughly 2,700 acres.
  3. Off-grid hub vs generator-only: generator energy about 982 to 584 GWh/yr, emissions about 768 to 457 kt CO2e, LCOE about $0.152 vs $0.20/kWh.
  4. Grid-connected hub vs grid-only: LCOE about $0.123 vs $0.14/kWh, emissions about 188 vs 285 kt CO2e (34% lower).
  5. Transition case: grid interconnection after 5 years at $240/kW, LCOE about $0.164/kWh.
  6. AI racks are cited as drawing roughly seven times the power of traditional racks.

Using it in design

  • Support phased supply scenarios (off-grid hub then grid) with PV, BESS and generator sizing in the site/energy module.
  • Output LCOE, emissions and land area, using about 6 acres per MW of PV.
  • Provide cost-input defaults with clear provenance and let the user override them.
  • Flag when the on-site PV land requirement exceeds the site area.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Compare the cost of design decisions

Evaluate equipment costs, energy expenses and total cost of ownership (TCO) using your inputs and assumptions in SoSo CAD.

Request a demo
CAPEX and TCO estimates in the SoSo CAD cost workspace

Who should read it

Planners and decision makers weighing energy and site strategy for large AI campuses whose grid connection will be delayed.

Related standards

  • GHG Protocol (Scope 2)

Publication details

Authors
Hitachi Energy
Publisher
Hitachi Energy
Year
2025
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Hitachi Energy (2025). Powering GenAI data centers at speed: A renewable energy hub approach from off-grid to grid-connected operation. Hitachi Energy. https://www.hitachi.com/content/dam/hitachi/us/en_us/insights/pdf/en_powering_genai_data_centers_at_speed.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.