Initial Proposal for a National Policy Statement (NPS) for Data Centres, October 2026
Original title Initial Proposal for a National Policy Statement (NPS) for Data Centres
UK Department for Business, Innovation, Science and Trade
The UK government's October 2026 initial NPS proposal: data centres of 100 MW or more rated IT load may be directed into the NSIP regime, and designs are expected to meet a PUE of 1.3 or better.
On this page
Overview
The document is the UK Department for Business, Innovation, Science and Trade's (DSIT) Initial Proposal for a National Policy Statement for Data Centres, dated October 2026 and presented to Parliament under section 9(2) of the Planning Act 2008. It sets out the reasons for considering data centres in England for development consent under the Nationally Significant Infrastructure Project (NSIP) regime of the Planning Act 2008, expectations of developers and decision criteria. It remains a proposal and is open to consultation.
On scope and threshold: projects operating at least 100 MW of rated IT load capacity are likely to be considered nationally significant and suitable for direction under section 35; this is an indicative minimum and smaller projects may be directed in exceptional circumstances. The decision maker (Secretary of State) starts from a presumption of consent for applications that meet the principles. The document recounts CNI designation, AI Growth Zones, the Data Centre Covenant and security and resilience measures as policy context.
The assessment principles section covers engagement, financial viability, environmental impact assessment, habitats and biodiversity net gain, criteria for good design, climate change mitigation and adaptation, national grid connection, environmental regulation, safety, security and health. The design section expects applicants to demonstrate that the design meets a PUE of 1.3 or better, to give reasons if a less resource-efficient design is chosen, and to reduce visual, noise and air impacts. The climate adaptation section asks for direct and indirect impacts over operational life, including flooding, drought, heat and wildfire (paragraph 171).
The generic impacts section covers air quality and emissions, biodiversity, historic environment, flood risk, coastal change, dust, odour, artificial light, landscape, land use and Green Belt, noise, socio-economic impacts, traffic, water quality and resources, and resource and waste management. The document is planning policy, not an engineering design specification.
Key points
- The proposal is dated October 2026 and presented to Parliament under section 9(2) of the Planning Act 2008; it gives the reasons for bringing data centres into the NSIP regime.
- Indicative threshold: at least 100 MW of rated IT load capacity; smaller projects may be directed in exceptional circumstances.
- The decision maker is to start from a presumption of consent for applications that meet the principles.
- Designs are expected to show a PUE of 1.3 or better; a rationale is required for a less efficient design.
- Climate adaptation: direct and indirect impacts over operational life such as flooding, drought, heat and wildfire (paragraph 171).
- Applicants are encouraged to appoint a design champion and use a representative design panel.
- Generic impacts include air quality (PM2.5, NOx), noise, water quality and resources, flood risk and waste management.
- The Data Centre Covenant's five tests (bills, community, environment, jobs, security) form the expectations framework.
Using it in design
- In the application show the PUE target of 1.3 or better by calculation, including part-load and summer conditions, and write the rationale for any less efficient choice.
- Prepare a lifetime climate resilience analysis covering flooding, drought, heat and wildfire and indirect dependencies such as access roads and grid connections.
- Within the EIA carry mitigation for generator and cooling emissions (PM2.5, NOx), noise, visual impact and water use into the design.
- Carry out flood risk, water source and waste management studies at site selection and attach the grid connection plan to the application.
- For projects near the 100 MW threshold weigh the NSIP direction request strategy together with the planning schedule.
Who should read it
Developers and planning and environmental consultants preparing development consent applications for large data centres in England.
Document contents
- Introduction
- Background to Data Centres
- Government Policy on Data Centre Development
- The Need for New Nationally Significant Data Centres
- Assessment Principles
- Generic Impacts
- Glossary
Publication details
- Authors
- UK Department for Business, Innovation, Science and Trade
- Publisher
- UK Department for Business, Innovation, Science and Trade
- Year
- 2026
- Document number
- ISBN 978-1-5286-6885-9
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
PDF p.4 expressly grants OGL v3.0 except where otherwise stated; identified third-party material requires separate permission. Draft status preserved. Round 5/6 ingestion retains bibliographic metadata only; no local full text is redistributed.
Citation
UK Department for Business, Innovation, Science and Trade (2026). Initial Proposal for a National Policy Statement (NPS) for Data Centres. UK Department for Business, Innovation, Science and Trade. ISBN 978-1-5286-6885-9. https://assets.publishing.service.gov.uk/media/6ae37e6183b993d8d93eb7d4/draft-national-policy-statement-for-data-centres.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.