SEIA Evaluation Criterion: Introduction to Data Centre Projects (Chile SEA, 2026)
Original title Criterio de evaluación en el SEIA: Introducción a proyectos de data center
Servicio de Evaluación Ambiental, Chile
Chile's Environmental Assessment Service (SEA) first-edition criterion of January 2026: SEIA entry for data centres is case by case, mainly through hazardous substances (80,000 kg) and secondarily through transmission lines above 23 kV.
On this page
Overview
The document is the first edition of 'Evaluation Criterion in the SEIA: Introduction to Data Centre Projects', put into effect by a resolution of 20 January 2026 by Chile's Environmental Assessment Service (SEA). It answers one of the nine strategic measures of the 2024-2030 National Data Centre Plan. Its aim is to give clear, uniform guidelines to those preparing and assessing environmental impact declarations (DIA) and environmental impact studies (EIA), introducing the main parts, works and equipment of data centres, associated impacts and contingency plans.
The document states that data centres have no explicit project typology for entry to Chile's environmental impact assessment system (SEIA); entry does not follow from being a data centre but is analysed case by case according to whether the parts and works match one of the types in Article 10 of Law 19,300. The main entry cause is hazardous substance handling (diesel fuel, refrigerants); a secondary cause is electrical transmission lines.
The entry causes are given numerically: high-voltage transmission lines above 23 kV (a pending Decree 17 will add a route length above 2 km); production, disposal or reuse of flammable substances of 80,000 kg per day or more, or storage capacity of 80,000 kg or more (the pending amendment sets the storage threshold at 1,000 tonnes); and the possibility of being a power plant over 3 MW is assessed case by case depending on the generator set configuration. Voltage step-down substations typically associated with data centres do not count under the b.2 entry item.
The document also defines data centre types by size (micro about 100 kW, small about 1 MW, medium about 10 MW, large 50 MW, hyperscale above 100 MW), presents cooling systems and energy alternatives (UPS, generators), lists likely impacts (soil, flora, fauna, air quality, water, health risk to the population, landscape value and others) and covers emergency plans and sectoral environmental permits. It is an environmental assessment guide and contains no engineering design specification.
Key points
- SEIA entry for data centres is determined case by case; there is no explicit data centre typology.
- Main entry cause is hazardous substances (diesel, refrigerants): flammable substance production/disposal of 80,000 kg per day or storage of 80,000 kg or more.
- A secondary cause is high-voltage transmission lines above 23 kV; pending Decree 17 will add a route length above 2 km.
- The pending amendment raises the flammable substance storage threshold to 1,000 tonnes.
- The over 3 MW power plant typology is assessed case by case by generator set configuration; emergency and backup (long-running) generators are treated separately.
- Voltage step-down substations do not fall under the transmission substation item.
- Large-scale operations may use 1-3 million litres of water per day for cooling (Minciencia, 2024).
- Size classes: micro ~100 kW, small ~1 MW, medium ~10 MW, large 50 MW, hyperscale above 100 MW.
Using it in design
- At project start compute diesel storage capacity and refrigerant inventory in kg and compare with the 80,000 kg threshold (1,000 t storage under the pending amendment).
- For Chilean projects with lines above 23 kV or generating units above 3 MW, run the SEIA entry analysis (pertinencia) at design stage and document the emergency versus backup generator distinction in the configuration.
- In cooling technology selection assess water consumption (1-3 million litres per day at large scale) together with energy consumption and carry it into the EIA/DIA file.
- Include hazardous substance stores, hazardous waste stores and emergency plans in the layout from the start of design.
- Add the sectoral environmental permit list (Annex 1) to the project schedule and permit matrix.
Who should read it
Developers, environmental consultants and designers preparing data centre projects for environmental permitting in Chile.
Document contents
- Presentation
- Summary
- Data Centre Development in Chile
- Types of Data Centres and Location
- Parts, Works and Equipment of a Data Centre
- SEIA Entry Typologies
- Identification of Potential Impacts
- Contingency Prevention and Emergency Plans
- Annex 1: Sectoral Environmental Permits
- Annex 2: Bibliography
Publication details
- Authors
- Servicio de Evaluación Ambiental, Chile
- Publisher
- Servicio de Evaluación Ambiental, Chile
- Year
- 2026
- Document number
- First edition, January 2026
- Document language
- Spanish
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official publisher document inspected. No document-specific commercial redistribution permission established; retain metadata and original short summaries only.
Citation
Servicio de Evaluación Ambiental, Chile (2026). Criterio de evaluación en el SEIA: Introducción a proyectos de data center. Servicio de Evaluación Ambiental, Chile. First edition, January 2026. https://sea.gob.cl/sites/default/files/imce/archivos/2026/01/20/DT_Datacenter.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.