Technical guideFree to read2026

Densification and the geometry of change: designing data centres in an age of uncertainty

Bryden Wood · Michael Hope-Jones

An article by Michael Hope-Jones of Bryden Wood on how rapidly rising rack densities change building form and delivery strategy, proposing two-speed delivery.

On this page

Overview

This article was published in 2026 by Michael Hope-Jones, MEP director at Bryden Wood, and discusses how rapidly rising rack densities change building form and delivery strategy. It is a consultancy viewpoint: not a standard or measurement report, and its recommendations rest on experience. It is thus a shared planning basis for architecture and engineering teams rather than a firm design rule.

According to the density figures cited, rack density moved from about 3-5 kW to 30-60 kW for hyperscalers and 80-150 kW for AI clusters, with some programmes considering 400 kW and more. Because projects take three to five years to deliver, a hall designed for 30 kW per rack may need to carry twice that at go-live. This uncertainty calls for keeping design decisions flexible at an early stage.

Hope-Jones recommends fixing column grids, load paths and cores early while deferring intermediate floors. Low-density air-cooled halls can be stacked two or three high, whereas high-density liquid-cooled IT belongs on the ground floor because of rack weight. CDU rooms, power and chilled water distribution and heat rejection should sit on upper levels above the high-density halls. The idea of two-speed delivery is to build plant early and fit out white space later.

One lesson drawn is that plant grows disproportionately with power and cooling, often eating the space saved by denser IT. As a limit, the article offers no quantitative calculation method; its figures show a trend and should be verified for a specific project. It still sets out, in a concrete frame, that building geometry, structural loading and delivery strategy must be treated together with density uncertainty.

Key points

  1. Rack density moved from about 3-5 kW to 30-60 kW for hyperscalers and 80-150 kW for AI clusters, with some programmes considering 400 kW+.
  2. Delivery takes three to five years, so a 30 kW/rack design may need to carry twice that at go-live.
  3. Low-density air-cooled halls can be stacked two or three high.
  4. High-density liquid-cooled IT belongs on the ground floor because of rack weight.
  5. Place CDU rooms, power and chilled water distribution and heat rejection on upper levels above high-density halls.
  6. Fix column grids, load paths and cores early while deferring intermediate floors.
  7. Two-speed delivery: build plant early, fit out white space later.
  8. Plant grows disproportionately with power and cooling, often eating the space saved by denser IT.

Using it in design

  • Warn when high-density liquid-cooled racks are placed on upper floors without a matching structural floor-load rating.
  • Show plant-space growth alongside white-space reduction when users raise rack density.
  • Set column grids and load paths for future density; keep intermediate floors deferrable.
  • Plan CDU, power and heat rejection areas above the high-density halls.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Check cooling capacity alongside your design

Review zone heat loads, available capacity and the capacity balance after the largest unit is lost in SoSo CAD.

Request a demo
Zone heat loads and capacity balance in the SoSo CAD cooling workspace

Who should read it

Data centre building, structural and MEP designers, programme managers and those setting delivery strategy under density uncertainty.

Publication details

Authors
Michael Hope-Jones
Publisher
Bryden Wood
Year
2026
Document language
English
Source type
Expert / community
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document