What You Need to Know About Arc Flash

Eaton · Adam Reeves, David G. Loucks

An introductory paper on arc-flash hazards and mitigation in commercial and industrial electrical systems, data centres included.

On this page

Overview

The paper frames the hazard through incident energy, the NFPA 70E / IEEE 1584 framework and labelling. NFPA 70E 130.5(G) requires the incident energy analysis to be updated at least every 5 years. The arc-flash boundary is where incident energy equals 1.2 cal/cm2, and labels are required on equipment over 50 V that may be accessed energised. Single-phase-to-ground faults are 7.8 (junctions) to 73 (cable) times more likely than three-phase faults (IEEE 493-2007), but IEEE 1584-2002 gives no method for them.

Mitigation is grouped into reducing available fault current (open tie during maintenance, smaller or higher-impedance transformers, high-resistance grounding, current-limiting devices), shortening clearing time (zone-selective interlocking, bus differential, maintenance-mode settings, arc-quenching switchgear), remote operation, predictive maintenance and redirecting blast energy. Opening the tie between dual feeds during maintenance roughly halves available fault current.

Eaton recommends separate line-side and load-side calculations for the main breaker, because line-side-only values can exceed 40 cal/cm2 and wrongly bar energised work. Main breakers can take up to 4 cycles (67 ms) to clear, while arc-quenching switchgear contains an arc in under 4 ms.

NEC prohibits high-resistance grounding on systems serving line-to-neutral loads such as most servers, which limits HRG to motor-only portions.

Key points

  1. NFPA 70E 130.5(G): the incident energy analysis must be updated at least every 5 years.
  2. Single-phase-to-ground faults are 7.8 (junctions) to 73 (cable) times more likely than three-phase faults (IEEE 493-2007); IEEE 1584-2002 gives no method.
  3. The arc-flash boundary is where incident energy equals 1.2 cal/cm2; labels are required on equipment over 50 V accessed energised.
  4. Eaton recommends separate line-side and load-side calculations for the main breaker; line-side-only values can exceed 40 cal/cm2 and wrongly bar energised work.
  5. Opening the tie between dual feeds during maintenance roughly halves available fault current.
  6. NEC prohibits HRG on systems serving line-to-neutral loads such as most servers; HRG is limited to motor-only portions.
  7. Main breakers can take up to 4 cycles (67 ms) to clear; arc-quenching switchgear contains an arc in under 4 ms.

Using it in design

  • Add arc-flash attributes per switchboard (available fault current, clearing time, maintenance-mode/ZSI availability, working distance) and compute incident energy per IEEE 1584 for line and load side.
  • Warn when incident energy exceeds 40 cal/cm2 or when breakers above the threshold ratings lack energy-reducing maintenance switching.
  • Prevent HRG selection on boards feeding line-to-neutral IT loads.
  • Flag closed-tie (double-ended) maintenance scenarios and generate label data.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Review your power design in SoSo CAD

Inspect supply paths, equipment loads and UPS failure scenarios in one model.

Request a demo
Single-line diagram in the SoSo CAD power and capacity workspace

Who should read it

Electrical engineers designing boards and maintenance procedures, and operational safety managers.

Related standards

  • NFPA 70E
  • IEEE 1584
  • IEEE 493
  • NEC 240.87
  • OSHA 29 CFR 1910.269

Publication details

Authors
Adam Reeves; David G. Loucks
Publisher
Eaton
Year
2018
Document number
WP083033EN
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Adam Reeves; David G. Loucks (2018). What You Need to Know About Arc Flash. Eaton. WP083033EN. https://web.archive.org/web/20220120090611/https://www.eaton.com/content/dam/eaton/company/news-insights/arc-flash-safety/what-you-need-to-know-about-arc-flash-wp083033en.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.