4 Common Causes of Generator or Switchgear Downtime (Michael Fluegeman, Antonio Tan III)
FacilitiesNet / Building Operating Management · Michael Fluegeman, Antonio Tan III
Part 2 of the same series, covering how standby generator systems fail: failure to start, failure to connect to the load, failure while running before utility returns, and failure to retransfer and shut down after utility returns.
On this page
Overview
This article is the second part of a series by Michael Fluegeman and Antonio Tan III, published in FacilitiesNet / Building Operating Management in 2020. It covers four failure modes of standby generator systems: failure to start, failure to connect to the load, failure while running before utility returns, and failure to retransfer and shut down after utility returns. Each mode is paired with checks and tests on ATS settings, breakers, batteries, fuel and extended runs.
Fail-to-start causes include controls not in automatic, failed cranking batteries or chargers, and an ATS that never sends the start signal; the test is to de-energize the ATS normal source. Fail-to-connect causes include wrong ATS neutral-switch timing, a genset main breaker left open and breakers set at minimum, causing nuisance trips. The series thus shows that many failures stem from configuration and testing gaps rather than from the equipment itself.
Failures during the run are often fuel delivery or contamination problems; running on generator for several hours is suggested to prove extended operation. In the fourth mode, generators may run indefinitely after utility returns if ATS timers require manual retransfer or if the in-phase monitor or engine frequency prevents closed transition. In lightly staffed sites, an unnoticed post-outage run risks fuel exhaustion.
The article offers a practical, experience-based checklist; it does not give numerical thresholds or standard requirements. Related documents include NFPA 110 and NFPA 70. As a limit, detailed settings should be set according to manufacturer documents and local regulation. In design terms, generator and ATS catalogue entries should include start-signal logic, neutral timing and in-phase monitor settings, and the commissioning plan should include ATS transfer and retransfer tests and an extended loaded run.
Key points
- Fail-to-start causes: controls not in automatic, failed cranking batteries or chargers, an ATS that never sends the start signal; test by de-energizing the ATS normal source.
- Fail-to-connect causes: wrong ATS neutral-switch timing, genset main breaker left open and breakers set at minimum causing nuisance trips.
- Failures during run are often fuel delivery or contamination problems; run on generator for several hours to prove extended operation.
- Generators may run indefinitely after utility returns if ATS timers require manual retransfer or the in-phase monitor/engine frequency prevents closed transition.
- In lightly staffed sites, an unnoticed post-outage run risks fuel exhaustion.
- Related documents: NFPA 110 and NFPA 70.
Using it in design
- Include start-signal logic, neutral timing and in-phase monitor settings in generator/ATS catalogue entries.
- Include ATS transfer and retransfer tests and an extended loaded run in the commissioning plan.
- Warn if no remote monitoring of genset run status is specified for unmanned sites.
- Add cranking batteries and chargers explicitly to the maintenance programme.
Monthly newsletter · free
Keep your reading list current
Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.
SoSo CAD
Review your power design in SoSo CAD
Inspect supply paths, equipment loads and UPS failure scenarios in one model.
Request a demo
Who should read it
Engineers and facility managers who design, commission and operate generators, ATS and switchgear.
Related standards
- NFPA 110
- NFPA 70
Publication details
- Authors
- Michael Fluegeman; Antonio Tan III
- Publisher
- FacilitiesNet / Building Operating Management
- Year
- 2020
- Document language
- English
- Source type
- Expert / community
- Access
- Free to read
- Licence
- Copyright retained; citation only — the publisher’s terms apply to the original document
Citation
Michael Fluegeman; Antonio Tan III (2020). 4 Common Causes of Generator or Switchgear Downtime (Michael Fluegeman, Antonio Tan III). FacilitiesNet / Building Operating Management. https://www.facilitiesnet.com/datacenters/article/4-Common-Causes-of-Generator-or-Switchgear-Downtime--18998
Events on this subject
- Electricity Eurasia 2027
- ELECO 2026 Elektrik-Elektronik ve Biyomedikal Mühendisliği Konferansı
- ICCI 2027 – Uluslararası Enerji ve Çevre Fuarı ve Konferansı
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.