White paperFree to read2013

Calculating Space and Power Density Requirements for Data Centers

Schneider Electric · Neil Rasmussen

A Schneider Electric white paper that gives a step-by-step method for specifying a data centre's IT load and space. It uses average and peak power per cabinet, estimate uncertainty and a managed-power ratio to derive rated system power and reserve space.

On this page

Overview

Neil Rasmussen's paper builds on the earlier WP 120 and gives a step-by-step method for specifying a data centre's IT load and space. The method uses four inputs: a design-target average kW per cabinet, peak cabinet power, the uncertainty of the estimate, and the expected "managed power", the ratio of typical draw to nameplate. Rated system power and expected operating load are derived from them.

Two worked examples are included: a 40 kW server room and a 2 MW multi-room facility. In the 40 kW example the target average is 4 kW per cabinet, peak is 8 kW, uncertainty is +/-15% at 80% confidence and the managed power ratio is 70%. The result is 48 kW of rated system power, 33.6 kW of expected IT, about 15% space reserve and a density of about 115 W/ft2. As a policy, peak cabinet power is capped at twice the design average (8 kW versus 4 kW in the example).

The author's main warning is against over-specifying density. A 1,000 W/ft2 (10,764 W/m2) data centre costs about 8 times as much as a 100 W/ft2 facility, and if it is operated at 100 W/ft2 its PUE is likely to be 3 to 5. Where little is known, typical values are suggested: a spec of 120 W/ft2 (1,292 W/m2) corresponds to about 3 to 5 kW per cabinet, and the example overall target density is 5 kW per cabinet, about 160 W/ft2 (1,722 W/m2). The method makes uncertainty in the IT load an explicit input rather than hiding it, which is its strength. Its limit is that results are only as good as the average and uncertainty values the designer estimates; the paper does not produce those for you.

Key points

  1. A typical spec of 120 W/ft2 (1,292 W/m2) corresponds to about 3 to 5 kW per cabinet.
  2. Example overall target density: 5 kW per cabinet, about 160 W/ft2 (1,722 W/m2).
  3. A 1,000 W/ft2 (10,764 W/m2) data centre costs about 8 times a 100 W/ft2 facility; operated at 100 W/ft2 its PUE is likely 3 to 5.
  4. 40 kW room example: target average 4 kW/cabinet, peak 8 kW, uncertainty +/-15% (80% confidence), managed power ratio 70%.
  5. Same example: rated system power 48 kW, expected IT 33.6 kW, about 15% space reserve, about 115 W/ft2.
  6. Policy: peak cabinet power is capped at 2 times the design average (8 kW versus 4 kW).

Using it in design

  • Use this paper as the template for the Design Basis form: target average kW per rack, peak kW per rack (default 2x average), density uncertainty (default 15%), managed power ratio (default 0.7) and reserve space (default 15%).
  • Compute rated system power as racks x average x (1 + uncertainty), and expected operating power as that value times the managed power ratio.
  • Warn when the specified average density exceeds 15 kW per rack without a liquid-cooling plan.
  • Warn when expected utilization will be low, since PUE will suffer; do not over-specify density.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Review your power design in SoSo CAD

Inspect supply paths, equipment loads and UPS failure scenarios in one model.

Request a demo
Single-line diagram in the SoSo CAD power and capacity workspace

Who should read it

Planners and engineers setting the design basis and capacity target of a new data centre.

Related standards

  • TIA-942
  • ASHRAE TC9.9 Thermal Guidelines

Publication details

Authors
Neil Rasmussen
Publisher
Schneider Electric
Year
2013
Document number
WP 155
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Neil Rasmussen (2013). Calculating Space and Power Density Requirements for Data Centers. Schneider Electric. WP 155. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_NRAN-8FL6LW_EN

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.