White paperFree to read2013

Considerations for Owning versus Outsourcing Data Center Physical Infrastructure

Schneider Electric · Wendy Torell, Kevin Brown

This 2013 Schneider Electric white paper compares upgrading an existing room, building a new facility and leasing retail colocation, using 10-year NPV TCO.

On this page

Overview

Four worked cases give capex per watt, 10-year TCO and the year in which cumulative in-house cost drops below colocation. Airflow upgrade: $2.10/W capex, $15/W TCO, under 1 year, 61% savings. High-density pod: $4.84/W, $20/W, 2 years, 50%. Facility modules: $8.45/W, $24/W, 3 years, 37%. New build: $11/W, $26/W, 5 years, 20%. Colocation 10-year TCO is taken as $39/W for the upgrade cases and $33/W for the scaled 1 MW new-build comparison.

In case 1, a Tier 3, 1 MW room limited to 900 kW by air mixing reclaims 100 kW with blanking panels, brush strips and cold-aisle containment for about $210K. Common assumptions: electricity $0.12/kWh, cost of capital 8%, 3%/yr escalation, 5 kW/rack, colocation at $1000/rack/month plus $925 power/rack/month, build PUE 1.5. Raising cost of capital from 3% to 8% narrows the build-versus-colocation gap from $13/W to $8/W.

Owning is cheaper over ten years in every case, but the advantage shrinks as project scope, cost of capital and short facility life increase. Traditional builds can take up to two years from concept to commissioning versus about 6-9 months for modular; colocation can be live in 1-2 months.

The paper adds decision filters: a need in under 6 months or a temporary need (under 5 years) rules out facility-module and new-build options, and a regulatory need to keep IT in-house rules out colocation. A ten-factor qualitative scorecard (10-100) covers non-financial preferences. Figures are 2013 US dollars.

Key points

  1. Case 1 airflow upgrade: $2.10/W capex, $15/W TCO, under 1 year cross-over, 61% savings.
  2. Case 4 new build: $11/W capex, $26/W TCO, 5 years, 20% savings.
  3. Colocation 10-year TCO: $39/W (upgrades), $33/W (scaled 1 MW new build).
  4. A Tier 3 room limited to 900 kW reclaims 100 kW for about $210K.
  5. Cost of capital from 3% to 8% narrows the gap from $13/W to $8/W.
  6. Timeframes: traditional up to 2 years, modular 6-9 months, colocation 1-2 months.
  7. Filter: a need under 6 months or under 5 years rules out facility modules and new build.
  8. Owning does not pay back if facility life is shorter than the cross-over year.

Using it in design

  • Offer an option-compare calculator (airflow upgrade, add pod, facility module, new build, colocation) with inputs mirroring Appendix A-D: electricity price, cost of capital, escalation, kW/rack, PUE, colocation fees.
  • Output capex $/W, 10-year NPV TCO $/W and cash cross-over year, seeding 2013 values only as clearly dated presets.
  • Flag that owning is unlikely to pay back when planned facility life is below the computed cross-over year.
  • Add a decision-filter step (deployment deadline, life expectancy, data residency) before showing costs.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Assess redundancy through scenarios

Compare normal operation and equipment failures in SoSo CAD, with supplied loads and capacity shortfalls in one view.

Request a demo
Normal operation and failure scenario comparison in SoSo CAD

Who should read it

Decision makers choosing between upgrading, building and leasing for new IT capacity.

Related standards

  • Uptime Institute Tier Standard: Topology

Publication details

Authors
Wendy Torell; Kevin Brown
Publisher
Schneider Electric
Year
2013
Document number
WP 171
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Wendy Torell; Kevin Brown (2013). Considerations for Owning versus Outsourcing Data Center Physical Infrastructure. Schneider Electric. WP 171. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_VAVR-8HF8DC_EN

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.