Research paperPDF2026

To Defer or To Shift? The Role of AI Data Center Flexibility on Grid Interconnection

arXiv preprint (University of Alberta) · Yize Chen, Xiaogui Zheng

The work embeds AI data-centre flexibility, both temporal deferral of compute within a completion window and geographic shifting between sites, in a grid capacity-expansion model with DC power-flow constraints, tested on the IEEE 14-bus and WECC 240-bus systems.

CC BY 4.0 — share with attribution

On this page

Overview

Integrating AI data centres into the power grid is among the most complex challenges for energy systems, and the traditional grid-planning paradigm of treating data centres as rigid, inflexible loads is becoming economically, mathematically and operationally untenable. A cited projection says U.S. AI data-centre demand could grow more than 30-fold to 123 GW by 2035 from 4 GW in 2024, and median time from interconnection request to commercial operation is over five years. The work tries to understand the large-load interconnection bottleneck by modelling AI load flexibility.

Depending on data-centre location, flexibility range and grid load conditions, flexible AI load reduced grid investment and operational costs by 3-21%. In one case flexibility reduced operating cost enough that the planner spent more on generation: total cost fell 3.5% while investment rose 7.1%. On the WECC 240-bus system the benefit of deferral was almost the same for delay windows of 3 hours or more, so short-term flexibility already captures most of the grid value. In the IEEE 14-bus study, data centres on buses connected to congested lines benefit most from geographic load shifting.

The finding is that flexibility lowers total system cost but does not always reduce the generation capacity that has to be built: its effect is not felt consistently, and more flexibility does not necessarily mean less generation capacity. Deferral windows longer than about 3 hours bring diminishing returns.

Limits: two test systems (IEEE 14-bus and WECC 240-bus) and a capacity-expansion model with DC power-flow constraints; results depend on these systems and the assumed flexibility participation rates. It is a preprint.

Key points

  1. Depending on data-centre location, flexibility range and grid load conditions, flexible AI load reduced grid investment and operational costs by 3-21%.
  2. Cited projection: U.S. AI data-centre demand could grow more than 30-fold to 123 GW by 2035 from 4 GW in 2024, and median time from interconnection request to commercial operation is over five years.
  3. In one case flexibility reduced operating cost enough that the planner spent more on generation: total cost fell 3.5% while investment rose 7.1%.
  4. On the WECC 240-bus system the benefit of deferral was almost the same for delay windows of 3 hours or more, so short-term flexibility already captures most of the grid value.
  5. In the IEEE 14-bus study, data centres on buses connected to congested lines benefit most from geographic load shifting.

Using it in design

  • In large-load interconnection negotiation, present AI load flexibility (a deferral window of up to about 3 hours) as a lever for interconnection capacity and timing; returns diminish beyond 3 hours.
  • Test in planning scenarios that flexibility does not always reduce generation investment (total cost fell 3.5% while investment rose 7.1%).
  • Assess the value of geographic load shifting separately for buses connected to congested lines.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Compare the cost of design decisions

Evaluate equipment costs, energy expenses and total cost of ownership (TCO) using your inputs and assumptions in SoSo CAD.

Request a demo
CAPEX and TCO estimates in the SoSo CAD cost workspace

Who should read it

Planners and grid specialists evaluating large data-centre load interconnection, grid capacity planning and load flexibility.

Document contents

  1. 1 Introduction
  2. 2 Capacity Expansion Model with Data Centers
  3. 3 Test systems and scenarios (IEEE 14-bus, WECC 240-bus)
  4. 4 Results
  5. 5 Conclusion and Future Works

Read the document

ai-dc-flexibility-interconnection-defer-shift-2026.pdf

PDF · 1.6 MB · English

CC BY 4.0 — share with attribution

The document is provided unaltered because its licence permits redistribution.

Publication details

Authors
Yize Chen; Xiaogui Zheng
Publisher
arXiv preprint (University of Alberta)
Year
2026
Document number
arXiv:2604.05376
Document language
English
Source type
Scientific
Access
Open licence — downloadable
Licence
CC BY 4.0 — share with attribution
Licence evidence
arxiv.org
Original licence note

arXiv record licence is http://creativecommons.org/licenses/by/4.0/ (checked via arXiv OAI-PMH)

Citation

Yize Chen; Xiaogui Zheng (2026). To Defer or To Shift? The Role of AI Data Center Flexibility on Grid Interconnection. arXiv preprint (University of Alberta). arXiv:2604.05376. https://doi.org/10.48550/arXiv.2604.05376

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.