White paperFree to read2025

Bending the Energy Curve: Decoupling Digitalization Trends from Data Center Energy Growth

Schneider Electric · Jim Simonelli, Victor Avelar et al.

A Schneider Electric white paper (WP 212, 2025) that explains why global data center electricity is forecast to grow strongly toward 2030 and compares the effect of the PUE lever against ICT efficiency in scenarios.

On this page

Overview

The paper examines why global data center electricity, flat during 2010-2020, is forecast to grow strongly toward 2030. Its analysis rests on the ratio of ICT energy to annual data generated. That ratio points to a compute-efficiency disruption from about 2020, with recovery expected later in the decade. The problem is therefore not only rising demand: energy per unit of data also worsened for a period.

The scenario section compares two levers. Reaching PUE 1.2 for new builds and 1.3 for 10% of existing sites by 2030 cuts data center energy by about 3.6% (about 38 TWh). Improvement in the ICT performance factor cuts energy by about 14.4% (about 153 TWh), roughly four times the PUE lever. The conclusion is that facility efficiency is useful but secondary.

ICT energy per unit of data is about 0.92 TWh/ZB in 2020 and is projected at 0.45 and 0.34 TWh/ZB by 2030 depending on the scenario. The paper also discusses grid-relief measures such as flexible load. These are forecasts, not measurements: results depend on assumed scenarios, so the relative size of the two levers is a safer reading than any single figure.

Key points

  1. Global data center electricity was flat in 2010-2020 and is forecast to grow strongly toward 2030.
  2. PUE 1.2 for new builds plus 1.3 for 10% of existing sites by 2030 cuts energy about 3.6% (about 38 TWh).
  3. ICT performance factor improvement cuts energy about 14.4% (about 153 TWh), roughly 4x the PUE lever.
  4. ICT energy per data generated was about 0.92 TWh/ZB in 2020.
  5. Projected 0.45 and 0.34 TWh/ZB by 2030 depending on scenario.
  6. A compute-efficiency disruption from about 2020 is followed by expected recovery later in the decade.
  7. Grid-relief measures such as flexible load are discussed.

Using it in design

  • In the energy dashboard, show IT-side levers (utilization, accelerated computing) next to facility PUE.
  • Add context text telling users that PUE improvement can be a small share of total energy impact.
  • Present flexible-load models as a separate scenario with grid effect.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Compare the cost of design decisions

Evaluate equipment costs, energy expenses and total cost of ownership (TCO) using your inputs and assumptions in SoSo CAD.

Request a demo
CAPEX and TCO estimates in the SoSo CAD cost workspace

Who should read it

Decision makers and sustainability teams doing energy strategy and capacity planning.

Related standards

  • ISO/IEC 30134-2
  • ISO/IEC 21836 (SEEM)

Publication details

Authors
Jim Simonelli; Victor Avelar; Wendy Torell
Publisher
Schneider Electric
Year
2025
Document number
WP 212
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Jim Simonelli; Victor Avelar; Wendy Torell (2025). Bending the Energy Curve: Decoupling Digitalization Trends from Data Center Energy Growth. Schneider Electric. WP 212. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_WP212_EN

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.