Accelerating AI Data Center Deployment with Software-Defined Medium-Voltage Switchgear
Schneider Electric · John Slater, Wendy Torell et al.
This paper compares traditional engineer-to-order MV switchgear with software-defined platforms. For a 20-panel example it quantifies the drop in wiring, terminals and schedule.
On this page
Overview
The paper compares traditional engineer-to-order (ETO) medium-voltage switchgear with software-defined platforms built on digital relays, low-power instrument transformers and configured functionality. The subject is shortening MV distribution lead time under the rapid-deployment pressure of AI data centres. The comparison uses a 20-panel, 34.5 kV, 2,500 A lineup. Control wiring falls from 4,800 m to 635 m, an 87 percent reduction; terminals fall from 12,000 to 1,120, 91 percent fewer; and copper use drops 85 percent. These reductions directly affect workshop and site labour.
The end-to-end schedule shrinks from 31.5 weeks to 11.5 weeks (64 percent shorter, 2.7 times faster). Engineering and manufacturing drops from 26 to 8.5 weeks, and installation and commissioning from 5 to 2.5 weeks. Campus MV distribution is commonly at 13.8 kV or 34.5 kV. The benefits go beyond schedule, extending to operational flexibility and reduced personnel exposure. Results rest on one example lineup, so gains may differ in other configurations, and manufacturer lead times should be confirmed per project.
Practical defaults for a schedule estimator can be drawn from the paper: about 26 to 32 weeks for traditional ETO MV switchgear and about 12 weeks for the software-defined option. The catalogue can hold MV voltage presets of 13.8/34.5 kV (North America) and 11/20/33 kV (IEC). On projects where lead time is critical, the two options should be compared side by side.
Key points
- End-to-end schedule 31.5 to 11.5 weeks (64 percent shorter, 2.7 times faster)
- Engineering and manufacturing 26 to 8.5 weeks; installation and commissioning 5 to 2.5 weeks
- 87 percent less control wire (4,800 to 635 m)
- 91 percent fewer terminals (12,000 to 1,120)
- 85 percent less copper
- Comparison case: 20-panel, 34.5 kV, 2,500 A lineup
- Campus MV distribution commonly at 13.8 kV or 34.5 kV
Using it in design
- In the schedule estimator, default MV switchgear lead time to about 26-32 weeks (ETO)
- Offer a software-defined option at about 12 weeks
- Keep MV voltage presets in the catalogue: 13.8/34.5 kV (North America), 11/20/33 kV (IEC)
- Include this option in comparisons for projects needing short lead times
Monthly newsletter · free
Keep your reading list current
Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.
SoSo CAD
Review your power design in SoSo CAD
Inspect supply paths, equipment loads and UPS failure scenarios in one model.
Request a demo
Who should read it
Project managers and MV designers of hyperscale and AI data centres targeting fast deployment.
Related standards
- IEC 62271-200
- IEC 61850
- IEEE C37.20.2
Publication details
- Authors
- John Slater; Wendy Torell; Venanzio Paolo Ferraro; Maxime Durand; Amita Sonar
- Publisher
- Schneider Electric
- Year
- 2026
- Document number
- WP 303
- Document language
- English
- Source type
- Manufacturer
- Access
- Free to read
- Licence
- Copyright retained; citation only — the publisher’s terms apply to the original document
Citation
John Slater; Wendy Torell; Venanzio Paolo Ferraro; Maxime Durand; Amita Sonar (2026). Accelerating AI Data Center Deployment with Software-Defined Medium-Voltage Switchgear. Schneider Electric. WP 303. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_WP303_EN
Events on this subject
Browse the events calendarAll content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.