BEAM Society Limited's September 2021 green-building assessment manual for new Hong Kong data centres: energy carries 40% of the weighting, design PUE is scored from 1.77 to 1.52, and the prerequisite PUE cap is 2.0.

On this page

Overview

BEAM Plus New Data Centres (NDC) Version 1.0 is a voluntary criteria set that rates the design and construction of data centres in Hong Kong at Platinum, Gold, Silver or Bronze level. The assessed area must be at least 500 m2, and staff and office support areas may not exceed 25% of it. Scope covers whole-building data centres, facilities converted from part of an industrial building, and existing buildings undergoing major alteration and addition works.

Credits fall into seven categories: Integrated Design and Construction Management (IDCM), Sustainable Site, Materials and Waste, Energy Use, Water Use, Health and Wellbeing, and Innovations and Additions. Category weights are IDCM 20%, energy 40% and the others 10% each. All prerequisites must be met, and bonus credits are multiplied by 1.2. Grade thresholds combine an overall score with an energy-category score: Platinum needs 70% overall and at least 75% in energy, Gold 60% and 65%, Silver 50% and 55%, Bronze 40% and 40%.

The energy category contains two PUE tests. Prerequisite EU-00-P1 requires a design PUE of no more than 2.0 at full IT load, plus compliance with the Hong Kong building energy code. Credit EU-01-02 scores the PUE calculated under Hong Kong climate at 75% of design IT load: 1 to 15 points for values between 1.77 and 1.52, with extra bonus points below 1.5 and 1.4. Cooling system efficiency in kW/ton is scored separately.

On water, cooling tower make-up, rainwater harvesting and recycling, effluent discharge and smart metering are separate objectives. On the delivery side, commissioning, BIM integration, a document management system and operating manuals are credit heads. Assessment does not begin until the facility is complete, so that design features are shown to be implemented. Supporting evidence must be captured at the time and cannot be assembled retrospectively.

Key points

  1. Category weights: IDCM 20%, energy use 40%, and sustainable site, materials and waste, water, and health and wellbeing 10% each.
  2. Grade thresholds (overall / energy category): Platinum 70% / at least 75%, Gold 60% / 65%, Silver 50% / 55%, Bronze 40% / 40%.
  3. Prerequisite EU-00-P1: design PUE of no more than 2.0 at full IT load.
  4. EU-01-02: PUE at 75% of IT load under Hong Kong climate earns 1 to 15 points between 1.77 and 1.52, with up to 2 extra bonus points below 1.5 and 1.4.
  5. EU-03-04 cooling system efficiency: thresholds of 0.85 and 0.78 kW/ton for air-cooled, 0.8 and 0.75 kW/ton for water-cooled systems (1 to 2 points).
  6. WU-01-06: at least 7 cycles of concentration in the cooling tower earns 1 point, 8 or more earns 1 bonus point.
  7. WU-02-01: a reduction of at least 20% in annual sewage volume earns 1 point.
  8. IDCM-03-04 BIM Integration offers 1 point plus 3 bonus points.
  9. The assessed area must be at least 500 m2, and associated function areas are capped at 25% of the floor area.
  10. Bonus credits carry a factor of 1.2 in the score calculation.

Using it in design

  • Calculate PUE both at 75% IT load and at full load with Hong Kong climate data; the prerequisite cap is 2.0 and the scoring band runs from 1.77 to 1.52.
  • Set the kW/ton target by system type in the cooling plan; for combined systems the assessment follows the dominant plant, which must account for at least 75% of actual cooling consumption.
  • Where a cooling tower is used, size make-up water treatment for at least 7, preferably 8 or more, cycles of concentration and include water meters in the design.
  • Plan the metering architecture for total facility power and IT power from the start so PUE can be measured (EU-01-04).
  • Build evidence-capture steps for commissioning, as-built BIM updates and document management into the project schedule; evidence cannot be prepared after the fact.

Who should read it

Mechanical, electrical and sustainability consultants designing data centres in Hong Kong, and owners seeking green-building certification.

Document contents

  1. Introduction (overview, framework, summary of credits)
  2. Integrated Design and Construction Management
  3. Sustainable Site
  4. Materials and Waste
  5. Energy Use
  6. Water Use
  7. Health and Wellbeing
  8. Innovations and Additions
  9. Appendices (glossary, energy modelling guideline, space types, stormwater detention O&M checklist)

Publication details

Authors
BEAM Society Limited
Publisher
BEAM Society Limited
Year
2021
Document number
Version 1.0, September 2021
Document language
English
Source type
Industry body
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Copyright 2021 BEAM Society Limited; all rights reserved. Only original framework and BIM credit content used; no ASHRAE-derived clauses summarized.

Citation

BEAM Society Limited (2021). BEAM Plus New Data Centres, Version 1.0. BEAM Society Limited. Version 1.0, September 2021. https://www.hkgbc.org.hk/eng/beam-plus/beam-plus-references/manuals-assessment/ManualsFiles/BEAMPlus-NDCV1-2021-EN.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cooling capacity in SoSo CAD

Check zone heat loads, installed capacity and the capacity left with the largest unit out, as part of the design.

Zone heat loads and capacity balance in the SoSo CAD cooling workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.