Johor State Data Centre Development Planning Guidelines

PLANMalaysia Johor

PLANMalaysia Johor's April 2024 guidelines split data centres into 1-5, 5-20 and 21-100 MW scales and set commercial-zone rules of at least 2 acres, 6 floors or 27 m height, 12 m setbacks and a 50 m buffer zone.

On this page

Overview

The guidelines were prepared following a 2023 resolution of the Johor State Planning Committee and approved by the State Executive Council in April 2024. They aim to offer a uniform, comprehensive planning manual, attract investors and create opportunities for SMEs. After definitions, classification (TIA-942 Tier I-IV), components and fibre routes, they give general and specific planning rules.

The scale table defines three classes: small (5,000-20,000 ft², 714-2,857 racks, 1-5 MW), medium (20,001-100,000 ft², 2,857-14,286 racks, 5-20 MW) and large (over 100,000 ft², over 14,286 racks, 21-100 MW). General rules list areas to avoid: flood and landslide areas, environmentally sensitive areas, peat, proximity to critical national targets, high-risk industry and aviation height-control radius.

Infrastructure requirements: a 33 kV substation for small centres and 132-275 kV for large ones; siting within 100 m of transmission lines or main intake substations is encouraged; industry best-practice PUE; dual service providers and at least 100 Mbps internet. For water, tank storage follows consumption, rainwater harvesting and eco-chillers are expected, and recognised water usage effectiveness standards apply.

Specific rules are given in separate tables for commercial and industrial zones and for existing or abandoned buildings, and the implementation mechanism defines the Data Centre Development Coordinating Committee and application process. It is a planning guideline, not a technical design standard, and gives no numeric PUE target.

Key points

  1. Scales: small 1-5 MW (714-2,857 racks), medium 5-20 MW (2,857-14,286 racks), large 21-100 MW (over 14,286 racks).
  2. Electrical: 33 kV substation for small, 132-275 kV for large; siting within 100 m of transmission lines or main intake substations is encouraged; electricity supply is approved by TNB.
  3. Internet: at least two service-provider infrastructures and at least 100 Mbps access speed.
  4. Commercial zone: minimum 2 acres (8,094 m²), maximum 6 floors or 27 m height, 12 m front, side, rear and between-building setbacks, and a minimum 50 m buffer zone.
  5. Industrial zone: minimum 1 acre (4,047 m²), maximum 4 floors or 27 m, built-up area 60% for 1-3 acres and 70% above 3 acres.
  6. Road reserves: local road 20 m; collector road 24 m in commercial and 30 m in industrial zones; parking 1 car per 46.41 m² of office GFA plus 10% for visitors.
  7. Areas to avoid: flooding and landslides, environmentally sensitive areas, peat, critical national targets, chemical and petroleum facilities, highways and railways, and aviation height-control radius.
  8. The TIA-942 table gives annual downtime of 28.8 hours (99.671%) for Tier I and 22 hours (99.741%) for Tier II.
  9. Water: storage tank size follows consumption; rainwater harvesting and eco-chillers are expected.

Using it in design

  • At pre-feasibility match the facility scale (MW, racks, ft²) to the small/medium/large classes and determine the substation voltage needed (33 kV or 132-275 kV).
  • Verify minimum lot, floors, setbacks and buffer zone for the commercial or industrial zone on the site plan; use the 12 m and 50 m clearances for fibre and utility corridors.
  • Add the areas to avoid (flood, landslide, peat, sensitive areas, aviation height limits) to the site-selection checklist.
  • Size the water storage tank from daily consumption and include the rainwater harvesting option in the water strategy.

Who should read it

Designers, planning consultants and state and local officials working on data-centre developments in Johor.

Document contents

  1. Introduction
  2. Interpretations
  3. General guidelines: location, electricity, water, internet, zones, land use
  4. Specific guidelines: commercial areas, industrial areas, existing or abandoned buildings
  5. Implementation mechanism
  6. Conclusion

Publication details

Authors
PLANMalaysia Johor
Publisher
PLANMalaysia Johor
Year
2024
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Public official source inspected. No document-specific commercial redistribution permission established. Metadata and original brief summaries only; local evidence is not a redistribution package.

Citation

PLANMalaysia Johor (2024). Johor State Data Centre Development Planning Guidelines. PLANMalaysia Johor. https://jpbd.johor.gov.my/wp-content/uploads/2025/02/81-GP-DATA-CENTRE-en.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cooling capacity in SoSo CAD

Check zone heat loads, installed capacity and the capacity left with the largest unit out, as part of the design.

Zone heat loads and capacity balance in the SoSo CAD cooling workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.