Technical guideFree to read2026

Guidance on the Redevelopment of Superfund and Brownfield Sites as AI Data Centers

U.S. Environmental Protection Agency

US EPA's January 2026 guidance EPA-540-S-26-001: criteria for evaluating Superfund and Brownfield sites for data centres, including at least 100 acres for a 100 MW campus, 2-5% slope, flood zone and remedy compatibility.

On this page

Overview

The document is guidance EPA-540-S-26-001 of the US Environmental Protection Agency (EPA), dated January 2026. It was prepared under Executive Order 14318 to expedite federal permitting and help return contaminated sites to productive use. It gives introductory information to community stakeholders and potential developers on how Superfund and Brownfield sites may be redeveloped as data centres.

The guidance separates the two site types by CERCLA definition. Superfund sites are where hazardous substances, pollutants or contaminants were improperly managed and EPA has cleanup authority; Brownfield sites are properties whose reuse is complicated by real or perceived contamination, where EPA does not regulate cleanup but provides funding and technical assistance, and state and Tribal governments set cleanup standards. This distinction shapes the redevelopment path.

The core conditions are threefold: the data centre must be compatible with site conditions, have easy access to infrastructure such as energy and fibre optic cables, and comply with all applicable local, state and federal regulations. The criteria table in Appendix A covers size and topography, population and location, energy, water, fibre connectivity, transport and supply chain, environmental conditions, flood and natural disaster risks, regional climate, remedy compatibility, EPA construction complete status, groundwater discharge, and regulatory and legal factors.

The legal and liability section says developers should address contamination liability risk from the start, pointing to Bona Fide Prospective Purchaser status, All Appropriate Inquiries (AAI) and No Further Action letters available from state regulators. The guidance is an introductory document; it gives no site-specific approval or technical design standard.

Key points

  1. A 100 MW campus-style data centre typically needs at least 100 acres; lower MW may fit on smaller sites.
  2. Slope: rectangular sites with slopes under about 2-5% are preferred; 5-10% is riskier and above 15-20% is not generally pursued.
  3. Ideally under one hour from a metropolitan area; proximity to fibre and internet exchanges often under 1 mile.
  4. Water: cooling may use millions of gallons per MW per year; 1-10 miles from the municipal supply; reuse of treated groundwater for cooling is possible.
  5. Most large data centres sit outside the 100-year flood zone; some prefer to be outside the 500-year zone.
  6. Cooling can account for 30-40% of energy consumption; cooler climates reduce it, and modern cooling makes warmer locations viable.
  7. On Superfund sites check EPA construction complete status, remedy compatibility and engineering/institutional controls.
  8. For Brownfield documentation a No Further Action letter from the state or Tribal regulator may be needed.

Using it in design

  • In the site screening table use rows for at least 100 acres per 100 MW, slope range (2-5% preferred), and power, water and fibre proximity.
  • Overlay foundations and excavations that affect capped soil and groundwater with the remedy plan and engineering controls; request a worker health and safety plan.
  • Assess flood zone position (100-year and 500-year) and other natural hazard risks together with insurance cost.
  • To use treated groundwater as cooling water, examine volume, quality and discharge permits.
  • Address legal risk early: put AAI, Bona Fide Prospective Purchaser status and regulator approval on the project critical path.

Who should read it

Developers, site engineers, local governments and community representatives siting data centres on contaminated or former industrial land.

Document contents

  1. Introduction
  2. Statutory Basis and Definitions for Superfund and Brownfield Sites
  3. Data Centers as a Redevelopment Opportunity
  4. Criteria and Considerations for Data Center Development
  5. Legal and Liability Considerations
  6. Conclusion
  7. Appendix A: Criteria for Data Center Consideration
  8. Appendix B: Superfund Redevelopment Resources
  9. Appendix C: Land Revitalization Resources

Publication details

Authors
U.S. Environmental Protection Agency
Publisher
U.S. Environmental Protection Agency
Year
2026
Document number
EPA-540-S-26-001
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official public publisher source inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only. Local downloads are research evidence, not a redistribution package.

Citation

U.S. Environmental Protection Agency (2026). Guidance on the Redevelopment of Superfund and Brownfield Sites as AI Data Centers. U.S. Environmental Protection Agency. EPA-540-S-26-001. https://www.epa.gov/system/files/documents/2026-01/guidance-on-the-redevelopment-of-superfund-and-brownfield-sites-as-ai-data-centers.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cooling capacity in SoSo CAD

Check zone heat loads, installed capacity and the capacity left with the largest unit out, as part of the design.

Zone heat loads and capacity balance in the SoSo CAD cooling workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.