SRBC says it takes a strong interest in any industry with potentially high water demand and, when hyperscale data-centre development began making headlines in the basin, found that water was mostly left out of the conversation, so it began educating developers, legislators, community planners and the public. Any data centre that proposes to withdraw or consumptively use water over the regulatory thresholds needs Commission approval before operating; hydrogeologists, geologists and engineers scientifically review whether the use would harm the environment or other users.
According to the page, depending on cooling technology demand can range from very low (under the thresholds) to millions of gallons per day and varies widely by company and site. As of early 2026 the Commission has issued only one permit for a hyperscale data centre in the basin (the Amazon Web Services complex in Salem Township, PA); much of the news is speculation rather than development. All approved projects and pending applications can be viewed in the Water Application and Approval Viewer (WAAV).
Approval routes: when a data centre is supplied from an existing public water system, no new withdrawal approval is needed because the water is already regulated through the public system. Commission approval is still required for consumptive use (water used but not returned to the basin) when it exceeds 20,000 gallons per day over a 30-day average. Consumptive uses supplied solely by public water supply, stormwater, wastewater or other reused or recycled water may receive an Approval by Rule, type (e), or ABR(e), a general permit in place since 2007 for all large water users. The Commission has made a determination affecting the public comment process for consumptive use by data centres on public supply; public hearing requirement and ABR(e) FAQ documents are published.
Key points
- Data centres withdrawing or consuming water over the thresholds need Commission approval before operating.
- Demand ranges from under the thresholds to millions of gallons per day depending on cooling technology.
- As of early 2026 only one hyperscale data centre permit has been issued in the basin (Salem Township, PA).
- A facility supplied from an existing public water system needs no new withdrawal approval.
- Consumptive use above 20,000 gallons per day over a 30-day average needs Commission approval.
- Consumptive use supplied by public water, stormwater, wastewater or recycled water may receive an ABR(e) general permit, in place since 2007.
- Withdrawal (water taken) and consumption (water not returned to the basin) are regulated separately.
- Approved and pending applications can be tracked in the WAAV viewer.
Using it in design
- For projects in the Susquehanna basin, compare estimated consumptive use with the 20,000 gallons per day (30-day average) threshold to determine early whether approval is needed.
- For sites on public supply, put the ABR(e) application for consumptive use, rather than a withdrawal approval, in the permitting schedule.
- Assess cooling technology (dry, hybrid, evaporative) for its effect on the consumptive-use threshold and approval process.
- Document water demand and consumption assumptions to prepare for the public comment and hearing process.
- Review approved and pending applications in WAAV for cumulative impact context.
Who should read it
Developers, permitting consultants and local planners developing data centres in the Susquehanna River Basin.
Document contents
- Overview
- FAQ: Water Use by Data Centers in the Susquehanna River Basin
- More Speculation than Development
- Data Center ABR(e) Approvals
- Articles and Interviews
Publication details
- Authors
- Susquehanna River Basin Commission
- Publisher
- Susquehanna River Basin Commission
- Year
- Year not stated
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official public publisher source inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only. Local downloads are research evidence, not a redistribution package.
Citation
Susquehanna River Basin Commission Data Centers & Water Use. Susquehanna River Basin Commission. https://www.srbc.gov/regulatory/data-centers/
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.