TESKON 2023 paper on the energy and carbon effect of waste-heat recovery in a test laboratory for indirect evaporative cooling (IEC) data-centre air handling units up to 500 kW.

On this page

Overview

This paper, in the TMMOB Chamber of Mechanical Engineers' TESKON 2023 proceedings, describes a Turkish manufacturer's factory test laboratory for indirect evaporative cooling (IEC) data-centre air handling units up to 500 kW. The laboratory has climatic and room-simulation cells, chillers for summer and winter simulation and a heat-recovery loop. Fan performance and heat-exchange tests follow ASHRAE 143-2015. The authors argue that every data-centre cooling unit should be performance-tested before shipment.

The paper shows that reusing chiller condenser heat to supply the room-simulation heat load cuts test energy sharply. Simulating the -5 °C winter condition at a 500 kW load, the test chillers (integrated COP 3.12) reject about 735 kW of waste heat that can supply the room-simulation cell. Waste-heat reuse saved about 75% versus a natural-gas boiler and about 94% versus electric heating for the test heat load. Operating cost and life-cycle carbon are compared for gas boiler, electric heater, electric boiler and waste-heat options.

Life-cycle GWP100 results for the four scenarios were 20.43, 41.87, 354.03 and 364.57 kg CO2-eq per test functional unit. Cooling is cited as historically about 50% of data-centre operating cost, reduced to about 34% with improved equipment. The climate cell uses a 7/12 °C chiller and a -10/-5 °C chiller to reproduce transitional and severe-winter conditions. The paper is useful background on how IEC data-centre units are rated and witness-tested.

Key points

  1. The lab tests IEC data-centre AHUs up to 500 kW cooling capacity; fan and heat-exchange tests follow ASHRAE 143-2015.
  2. Simulating -5 °C winter at 500 kW, test chillers (integrated COP 3.12) reject about 735 kW of waste heat.
  3. Waste-heat reuse saved about 75% versus a natural-gas boiler and about 94% versus electric heating for the test heat load.
  4. Life-cycle GWP100 results for four scenarios: 20.43, 41.87, 354.03 and 364.57 kg CO2-eq per test functional unit.
  5. Cooling is cited as historically about 50% of data-centre operating cost, reduced to about 34% with improved equipment.
  6. The climate cell uses a 7/12 °C chiller and a -10/-5 °C chiller for transitional and severe-winter conditions.
  7. Related standards: ASHRAE 143-2015, EN 308, ISO 14044, ISO 14064-1.

Using it in design

  • In the catalogue, add test-standard and witness-test fields for IEC/DC AHUs: ASHRAE 143 rating, tested capacity, factory witness test yes/no.
  • In the commissioning checklist, prompt for a factory acceptance test of each data-centre cooling unit at site design conditions, including winter mode.
  • Evaluate waste-heat recovery in test or manufacturing facilities for energy and carbon.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Check cooling capacity alongside your design

Review zone heat loads, available capacity and the capacity balance after the largest unit is lost in SoSo CAD.

Request a demo
Zone heat loads and capacity balance in the SoSo CAD cooling workspace

Who should read it

Mechanical engineers and manufacturers who specify, rate and commission data-centre cooling units.

Related standards

  • ASHRAE 143-2015
  • EN 308
  • ISO 14044
  • ISO 14064-1

Publication details

Authors
Ahmet Murat Tunç; Nadide Asuman Yaraş
Publisher
TMMOB Makina Mühendisleri Odası (MMO)
Year
2023
Document number
TESKON 2023 Bildiriler Kitabı, s. 944
Event
15. Ulusal Tesisat Mühendisliği Kongresi (TESKON 2023), İzmir
Document language
English
Source type
Industry body
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Ahmet Murat Tunç; Nadide Asuman Yaraş (2023). Veri Merkezi Klima Santrali Test Laboratuvarlarında Atık Isının Kullanımı Yöntemiyle Enerji Tasarrufu ve Karbon Ayak İzine Etkisi (Energy saving and carbon footprint effect of waste-heat use in data-centre AHU test laboratories). TMMOB Makina Mühendisleri Odası (MMO). TESKON 2023 Bildiriler Kitabı, s. 944. 15. Ulusal Tesisat Mühendisliği Kongresi (TESKON 2023), İzmir. https://mmoteskon.org/images/2025/05/teskon-2023-bildiriler-kitabi-3.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.