AI Data Center Siting on Federal Lands: An Energy View

RAND

RAND report RR-A5050-1 presents a quantitative model that ranks 31 candidate federal locations for a 1 GW data centre under four generation scenarios by energy infrastructure cost and readiness.

On this page

Overview

RAND evaluates federal-land data-centre siting through energy infrastructure costs and readiness. The public research overview explains the scenario-based site rankings and the need for public-private coordination. The report number is RR-A5050-1.

A quantitative model compares 31 candidate locations for a 1 GW data centre under four generation scenarios. Rankings are sensitive to compute scale, financing cost and cooling requirements, so the results depend on the scenario rather than giving a single fixed site list.

Key points

  1. A quantitative model compares 31 candidate locations for a 1 GW data centre.
  2. Four different generation scenarios are used.
  3. Site rankings are sensitive to compute scale.
  4. Rankings are sensitive to financing cost.
  5. Rankings are sensitive to cooling requirements.

Using it in design

  • In site screening treat energy infrastructure cost and readiness as a criterion independent of land ownership.
  • Test the site comparison against several generation scenarios rather than a single one.
  • Include financing cost and cooling requirement assumptions in sensitivity analysis.
  • Treat the need for public-private coordination as a schedule risk.

Who should read it

Policy makers, developers and energy planners assessing large-scale data centre siting on federal land.

Publication details

Authors
RAND
Publisher
RAND
Year
2026
Document number
RR-A5050-1
Document language
English
Source type
Industry body
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Public report overview read; linked full report not claimed as completely reviewed. No commercial redistribution permission established.

Citation

RAND (2026). AI Data Center Siting on Federal Lands: An Energy View. RAND. RR-A5050-1. https://www.rand.org/pubs/research_reports/RRA5050-1.html

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.