Technical guideFree to read2025

Hyperscale Data Centers and How to Power Them

Burns & McDonnell (BenchMark) · Keegan Odle, Tom Parker et al.

This Burns & McDonnell BenchMark article discusses how hyperscale campuses get power when utility capacity lags. It covers islanded rapid-deployment microgrids, energy storage and longer-term options such as SMRs.

On this page

Overview

The article is a BenchMark piece in which Burns & McDonnell power and mission-critical leaders discuss how hyperscale campuses obtain power when utility capacity lags. Its authors are Keegan Odle, Tom Parker, Chris Ruckman and Christine Wood, and it is dated 2025.

According to the text, hyperscale campuses commonly range from 60 MW to several hundred MW; 12 MW used to be considered large. Rapid-deployment microgrids run reciprocating engines and/or industrial turbines in parallel, islanded, until utility capacity arrives, and later transition to utility service. These can be supported by energy storage and by longer-term options.

On storage, long-duration storage of 12+ hours is promising but still needs lower capex and scaled manufacturing. SMRs are not expected to be viable for another six to eight years. The article also notes that hybrid modular/prefabricated construction is more common than fully modular builds.

The lessons are practical: give the utility an accurate load-ramp schedule, sign the service agreement early and build close to existing transmission. The article is a consultancy viewpoint and contains no detailed engineering calculation or cost data.

Key points

  1. Hyperscale campuses commonly range from 60 MW to several hundred MW; 12 MW used to be considered large.
  2. Rapid-deployment microgrids run reciprocating engines and/or industrial turbines in parallel, islanded, until utility capacity arrives.
  3. Long-duration storage of 12+ hours is promising but needs lower capex and scaled manufacturing.
  4. SMRs are not expected to be viable for another six to eight years.
  5. Lesson: give the utility an accurate load-ramp schedule, sign the service agreement early, build close to existing transmission.
  6. Hybrid modular/prefabricated construction is more common than fully modular builds.
  7. Authors: Keegan Odle, Tom Parker, Chris Ruckman, Christine Wood; 2025.

Using it in design

  • Capture a phased load-ramp schedule (MW by date) as a first-class input.
  • Let the electrical concept include a temporary islanded generation phase before utility connection.
  • Warn when the ramp exceeds the confirmed utility capacity for a phase.
  • In site selection, treat proximity to existing transmission as a criterion.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Review your power design in SoSo CAD

Inspect supply paths, equipment loads and UPS failure scenarios in one model.

Request a demo
Single-line diagram in the SoSo CAD power and capacity workspace

Who should read it

Electrical designers, developers and energy strategists planning power supply for hyperscale campuses.

Publication details

Authors
Keegan Odle; Tom Parker; Chris Ruckman; Christine Wood
Publisher
Burns & McDonnell (BenchMark)
Year
2025
Document language
English
Source type
Expert / community
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Keegan Odle; Tom Parker; Chris Ruckman; Christine Wood (2025). Hyperscale Data Centers and How to Power Them. Burns & McDonnell (BenchMark). https://info.burnsmcd.com/benchmark/article/hyperscale-data-centers-and-how-to-power-them

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.