Data Center Projects: Standardized Process
Schneider Electric · Neil Rasmussen, Suzanne Niles
Schneider Electric WP 140 proposes a standardized, configurable process for data centre physical-infrastructure build and upgrade projects, separating the system being built from the process that creates it.
On this page
Overview
The process has four sequential phases: Prepare, Design, Acquire and Implement. Prepare and Design form the PLAN portion; Acquire and Implement form the BUILD portion. Each phase is made of steps with an owner, a task list, and defined inputs and outputs, and each ends in a milestone: commit to project, purchase order submitted, equipment delivered, and project complete.
What turns an upgrade into a 'project' is a change in power or cooling architecture, the introduction of risk, a need for planning and coordination, or a need to shut down equipment. Three asynchronous activities can be triggered at any point: project change management, product defect correction and process defect correction. Engineered-to-order projects add steps for custom solution design, factory acceptance test and commissioning, which is whole-system testing after installation.
Every step has an owner, a task list (work instructions plus a checklist), inputs that are outputs of earlier steps, and outputs needed downstream. This creates a pull-based flow in which every output feeds a downstream step. The Start-up step comprises five tasks: verify correct assembly, verify operating mode, third-party device configuration, basic software configuration and basic operator training.
The paper stresses explicit responsibility assignment. A responsibility checklist assigns every process step to the user, the primary equipment vendor or a third party, or marks it not needed. The text makes no quantitative performance claim; its value is in writing down in advance who owns each step and where each output goes.
Key points
- Four phases: Prepare and Design form PLAN; Acquire and Implement form BUILD.
- Milestones: commit to project, purchase order submitted, equipment delivered, project complete.
- A change in power or cooling architecture, risk, need for planning/coordination or equipment shutdown elevates an upgrade to a 'project'.
- Three asynchronous activities: project change management, product defect correction, process defect correction.
- Engineered-to-order projects add custom solution design, factory acceptance test and commissioning.
- Start-up has five tasks: verify assembly, verify operating mode, third-party device configuration, basic software configuration, basic operator training.
- Every step has an owner, task list, inputs from earlier outputs and outputs for downstream steps.
- A responsibility checklist assigns each step to user, primary vendor, third party or not needed.
Using it in design
- Model the project workspace as phases, steps and milestones (Prepare, Design, Acquire, Implement), tying each deliverable to an owner and to the downstream step that consumes it.
- Add a responsibility matrix (user / vendor / third party / not needed) and block milestone sign-off while any step is unassigned.
- Auto-insert factory acceptance test and commissioning tasks when the design contains engineered-to-order equipment.
- Keep a change log and defect register available at every phase and export a start-up checklist from the design's equipment list.
Monthly newsletter · free
Keep your reading list current
Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.
SoSo CAD
Bring standards pre-checks into your project
Review model-based TS EN 50600 and Tier pre-checks, missing inputs and items requiring engineering review in SoSo CAD.
Request a demo
Who should read it
Project managers running data centre builds and teams defining a design workflow.
Publication details
- Authors
- Neil Rasmussen; Suzanne Niles
- Publisher
- Schneider Electric
- Year
- 2011
- Document number
- WP 140
- Document language
- English
- Source type
- Manufacturer
- Access
- Free to read
- Licence
- Copyright retained; citation only — the publisher’s terms apply to the original document
Citation
Neil Rasmussen; Suzanne Niles (2011). Data Center Projects: Standardized Process. Schneider Electric. WP 140. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_DBOY-6KVM82_EN