This 17 June 2024 article from Turner & Townsend, written by Simon Kearney, offers a view of how data centres are delivered in Asia-Pacific in an AI-driven world. It is freely readable and draws on the firm's 2023 cost index survey, which examined 46 markets. It is the perspective of a consultancy and not an independent academic study.

The article's main message is that access to power dominates site selection: 92% of surveyed respondents rank access to power above location. At a time when AI workloads push up power demand, this shows that a site's value is set more by grid connection and capacity than by geographic appeal. On cost, in the 2023 index costs rose by 13% in Jakarta and 10% in Kuala Lumpur, examples of the large cost rises in emerging markets. Singapore ranked as the fifth most expensive market after Tokyo, Zurich and Silicon Valley. The article also notes that renewables integration is growing.

The article's limit is that it rests only on a survey and an opinion piece; method detail and raw data are not presented here. The figures should therefore be read as indicators of the regional trend rather than exact values. The practical takeaway for teams doing site screening is to weight power availability heavily and apply market cost escalation factors.

Key points

  1. 92% of surveyed respondents rank access to power above location.
  2. Jakarta and Kuala Lumpur costs rose 13% and 10% in 2023.
  3. Singapore is the fifth most expensive market after Tokyo, Zurich and Silicon Valley in the 2023 index.
  4. The 2023 cost index examined 46 markets.
  5. The article is dated 17 June 2024 and focuses on Asia-Pacific data centre delivery.
  6. Renewables integration is growing.
  7. A consultancy's perspective; freely readable.

Using it in design

  • In APAC site screening, weight power availability heavily.
  • Apply market cost escalation factors.
  • Set budget assumptions separately for high-cost markets such as Singapore and Tokyo.
  • Treat renewables integration as a criterion in site scoring.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Compare the cost of design decisions

Evaluate equipment costs, energy expenses and total cost of ownership (TCO) using your inputs and assumptions in SoSo CAD.

Request a demo
CAPEX and TCO estimates in the SoSo CAD cost workspace

Who should read it

Investors, project managers and planning engineers setting site selection, budget and delivery strategy in Asia-Pacific.

Publication details

Authors
Simon Kearney
Publisher
Turner & Townsend
Year
2024
Document language
English
Source type
Expert / community
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document
Original licence note

Public web article; cited only.

Citation

Simon Kearney (2024). Delivering Data Centres in an AI-Driven World (APAC perspective). Turner & Townsend. https://www.turnerandtownsend.com/insights/delivering-data-centres-in-an-ai-driven-world/

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.