This paper compares Uptime Institute Tiers, TIA-942 rating levels and Syska criticality levels, and proposes describing business need with criticality levels C1-C4. It also shows how the chosen level drives lifetime cost.
On this page
Overview
The paper reviews three common classification systems: Uptime Institute Tiers, TIA-942 rating levels and Syska Criticality Levels. It concludes that all converge on four broad levels but lack the detail needed for a defensible specification. The four TIA-942 levels are based on Uptime's Tier Standard, while Syska defines ten levels that map onto four. The paper's aim is to replace vague Tier claims with measurable criteria, and to give teams that use different systems a common specification language.
The proposal is to use criticality C1-C4 to describe the business need, and to build a balanced design in which no subsystem is weaker than the target. Business characteristics and design effects are tabulated per level. C1 accepts UPS-only with at least 8 minutes of backup and tolerates outages of about 10 minutes. C2 adds generator backup and can sustain a 24-hour outage. C3 has redundant power and cooling, concurrent maintenance, 72-hour endurance, two utility paths and a 1-hour fire rating.
C4 provides 2N power and cooling, two independent utility paths, 96-hour endurance, a fire rating of at least 2 hours and 24/7 onsite staff. Fit-out cost estimates for power and cooling are $11.5/W for C1, $12.5/W for C2, $25/W for C3 and $28/W for C4, with core and shell at roughly $300/ft² ($2,880/m²). The paper stresses that criticality drives lifetime total cost of ownership, especially through the energy used by redundant systems. A limit is that the cost figures are estimates tied to a particular year and set of assumptions, so they need adjusting for local conditions. Even so, it offers a practical framework for giving owners and designers a shared vocabulary.
Key points
- C1: UPS-only acceptable with at least 8 minutes of backup; tolerates about 10-minute outages; many single points of failure.
- C2: generator backup; able to sustain a 24-hour outage; some power and cooling redundancy.
- C3: redundant power and cooling, concurrent maintenance, 72-hour endurance, two utility paths (active/passive), 1-hour fire rating.
- C4: 2N power and cooling, two independent utility paths, 96-hour endurance, at least 2-hour fire rating, 24/7 onsite staff.
- Fit-out cost (power+cooling): C1 $11.5/W; C2 $12.5/W; C3 $25/W; C4 $28/W; core and shell about $300/ft² ($2,880/m²).
- The four TIA-942 levels are based on Uptime's Tier Standard; Syska maps ten levels onto four.
- No subsystem should be weaker than the target criticality (balanced design).
Using it in design
- Build a novice criticality wizard (C1-C4) and map defaults to it: fuel autonomy 0/24/72/96 h, utility feeds 1/1/2/2, fire rating 0/0/1/2 h.
- Map redundancy defaults to N / N+1 / N+1 concurrently maintainable / 2N.
- Show the $/W cost multipliers as editable estimate defaults.
- Enforce the balanced rule: overall rating equals the lowest subsystem rating.
Monthly newsletter · free
Keep your reading list current
Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.
SoSo CAD
Assess redundancy through scenarios
Compare normal operation and equipment failures in SoSo CAD, with supplied loads and capacity shortfalls in one view.
Request a demo
Who should read it
Owners, consultants and design engineers choosing the target criticality level for a data centre.
Related standards
- Uptime Tier Standard: Topology
- TIA-942
- EN 50600-1
- BICSI 002
Publication details
- Authors
- Victor Avelar
- Publisher
- Schneider Electric
- Year
- 2015
- Document number
- WP 122
- Document language
- English
- Source type
- Manufacturer
- Access
- Free to read
- Licence
- Copyright retained; citation only — the publisher’s terms apply to the original document
Citation
Victor Avelar (2015). Guidelines for Specifying Data Center Criticality / Tier Levels. Schneider Electric. WP 122. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_VAVR-6PHPBU_EN
Events on this subject
Browse the events calendarAll content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.