Avoiding Costs from Oversizing Data Center and Network Room Infrastructure
In the capacity planner keep design, installed and expected-load curves separate per phase and show utilisation over a 10-year horizon; default start-up load to 20-30% of design and final load to 60-90%.
- Total excess lifecycle cost from oversizing averages about 30%.